Highway Engineering: Pavement Materials & Construction

Civil Engineering · Highway Engineering

48 questions, each with the answer and a worked solution.

Practice interactively and track your score →
Question 1

The top layer of the prepared natural ground on which the pavement layers rest is called the:

  1. base course
  2. wearing course
  3. sub-grade
  4. soling layer
Show answer & solution

Answer: (C) sub-grade

The subgrade is the compacted natural soil that supports the pavement structure.

Question 2

The strength of the subgrade is important because it influences:

  1. the super-elevation needed on curves and ramps
  2. the sight distance available to drivers ahead
  3. the camber provided on the surface layer
  4. the pavement thickness and performance
Show answer & solution

Answer: (D) the pavement thickness and performance

A weaker subgrade needs a thicker pavement to spread the load.

Question 3

The California Bearing Ratio (CBR) test measures the:

  1. shearing resistance of soil at controlled moisture and density
  2. viscosity of bitumen at a standard test temperature
  3. compressive strength of concrete cubes after 28 days of curing
  4. abrasion loss of coarse aggregates in a rotating drum
Show answer & solution

Answer: (A) shearing resistance of soil at controlled moisture and density

CBR is a penetration test that rates the strength of subgrade and base materials.

Question 4

A higher CBR value of a subgrade generally indicates:

  1. a weaker subgrade that needs thicker pavement layers
  2. a stronger subgrade that permits thinner pavement layers
  3. a soil that is unsuitable for road construction
  4. a subgrade with a higher swelling potential
Show answer & solution

Answer: (B) a stronger subgrade that permits thinner pavement layers

High CBR means better bearing strength, so less pavement thickness is needed.

Question 5

In the CBR test, the soil's resistance to penetration is compared with that of:

  1. a clay at its liquid limit
  2. a standard dry sand
  3. a standard crushed stone
  4. a concrete of grade M20
Show answer & solution

Answer: (C) a standard crushed stone

CBR (%) = test load / standard load for the same penetration in crushed stone × 100.

Question 6

Subgrade preparation for pavement construction mainly includes:

  1. laying the wearing course directly on the natural soil
  2. applying a tack coat over the natural ground surface
  3. cutting dowel slots in the compacted soil layer
  4. compacting to specified density and removing soft spots
Show answer & solution

Answer: (D) compacting to specified density and removing soft spots

A uniform, well-compacted subgrade gives even support to the pavement.

Question 7

The Proctor compaction test is used to determine the:

  1. coefficient of permeability of the soil
  2. maximum dry density and optimum moisture content
  3. California bearing ratio of the soil
  4. liquid limit of the fine-grained soil
Show answer & solution

Answer: (B) maximum dry density and optimum moisture content

Proctor tests give the moisture content at which the soil reaches its maximum dry density.

Question 8

The field density of a compacted layer is checked mainly to:

  1. verify that the specified compaction was achieved
  2. measure the bitumen content of the compacted layer
  3. check the thickness of the finished wearing course
  4. measure the surface roughness of the finished layer
Show answer & solution

Answer: (A) verify that the specified compaction was achieved

Field density is compared with the laboratory maximum density to get the percentage compaction.

Question 9

Which set of properties is normally tested for road aggregates?

  1. viscosity, flash point, fire point and solubility
  2. strength, toughness, abrasion resistance, soundness, shape
  3. slump, setting time, workability and compressive strength
  4. penetration, ductility, softening point and flash point
Show answer & solution

Answer: (B) strength, toughness, abrasion resistance, soundness, shape

Aggregate tests include crushing, impact, abrasion, soundness and shape tests.

Question 10

The Los Angeles abrasion test on road aggregates evaluates their resistance to:

  1. weathering from repeated freeze–thaw cycles
  2. stripping of the bitumen film by water
  3. absorption of water into the aggregate pores
  4. fragmentation and mechanical wear
Show answer & solution

Answer: (D) fragmentation and mechanical wear

The LA test gauges hardness by tumbling aggregate with steel balls.

Question 11

The soundness test on road aggregates determines their resistance to:

  1. shear deformation under sustained heavy loading
  2. wear caused by the friction of repeated wheel loads
  3. weathering from freeze–thaw or chemical action
  4. fracture caused by sudden impact shock loads
Show answer & solution

Answer: (C) weathering from freeze–thaw or chemical action

Soundness is tested by repeated cycles of soaking in sodium or magnesium sulphate solution.

Question 12

Flakiness and elongation indices determine the:

  1. shape characteristics of coarse aggregates
  2. specific gravity of the aggregate particles
  3. porosity of the aggregate in a saturated state
  4. ductility of the bitumen binder at 27 °C
Show answer & solution

Answer: (A) shape characteristics of coarse aggregates

Flaky and elongated particles are undesirable, so their proportion is limited.

Question 13

The aggregate impact value test measures the aggregate's:

  1. adhesion to the bitumen film on the stone
  2. toughness, i.e. resistance to sudden shock
  3. water absorption capacity of the pores
  4. resistance to abrasion by steel balls
Show answer & solution

Answer: (B) toughness, i.e. resistance to sudden shock

The impact test rates how well aggregate resists fracture under a falling hammer.

Question 14

The aggregate crushing value indicates the aggregate's resistance to:

  1. crushing under a gradually applied compressive load
  2. weathering by repeated wetting and drying cycles
  3. defects arising from poor particle shape
  4. stripping of the bitumen film in water
Show answer & solution

Answer: (A) crushing under a gradually applied compressive load

A low crushing value means stronger aggregate.

Question 15

The stripping value test of aggregate assesses:

  1. specific gravity of the aggregate when saturated in water
  2. resistance of the aggregate to freezing and thawing cycles
  3. shape of the coarse aggregate particles in a sample
  4. adhesion between aggregate and bitumen in the presence of water
Show answer & solution

Answer: (D) adhesion between aggregate and bitumen in the presence of water

Stripping occurs when water displaces the bitumen film from the aggregate surface.

Question 16

For pavement layers, coarse aggregate particles should preferably be:

  1. flaky and thin
  2. rounded and smooth
  3. cubical and angular
  4. elongated and needle-like
Show answer & solution

Answer: (C) cubical and angular

Cubical, angular particles interlock well and give high stability.

Question 17

A well-graded aggregate is preferred for dense mixes because it:

  1. needs no binder, giving a cheaper mix
  2. has particles of a single size, giving a uniform mix
  3. contains only fine particles, giving a smooth mix
  4. has few voids and good interlock, giving a dense mix
Show answer & solution

Answer: (D) has few voids and good interlock, giving a dense mix

Graded sizes fill each other's voids and increase density and stability.

Question 18

The penetration test on bitumen measures its:

  1. ductility under tension
  2. hardness or consistency
  3. softening point on heating
  4. flash point on heating
Show answer & solution

Answer: (B) hardness or consistency

Penetration is the depth in 0.1 mm that a standard needle sinks into bitumen under standard conditions.

Question 19

A bitumen of grade 80/100 means that its penetration at 25 °C is:

  1. between 8 and 10 in units of 0.1 mm
  2. between 80 and 100 seconds of flow
  3. between 80 and 100 in units of 0.1 mm
  4. between 80 and 100 millimetres
Show answer & solution

Answer: (C) between 80 and 100 in units of 0.1 mm

Penetration grades specify the penetration range in tenths of a millimetre.

Question 20

The ductility test of bitumen measures:

  1. the distance a briquette stretches before breaking
  2. the temperature at which it softens in a ring
  3. the hardness of the bitumen at 25 °C under a needle
  4. the temperature at which its vapours ignite
Show answer & solution

Answer: (A) the distance a briquette stretches before breaking

Ductility indicates the binder's ability to stretch without cracking.

Question 21

The ring-and-ball test on bitumen gives its:

  1. penetration value
  2. softening point
  3. ductility value
  4. flash point
Show answer & solution

Answer: (B) softening point

It records the temperature at which the bitumen softens enough to sag a set distance.

Question 22

The flash point of bitumen indicates the:

  1. highest temperature for safe heating without fire hazard
  2. hardness of the bitumen at 25 °C under a needle
  3. viscosity of the bitumen at 60 °C in a tube
  4. temperature at which the bitumen begins to soften in a ring
Show answer & solution

Answer: (A) highest temperature for safe heating without fire hazard

Heating above the flash point risks ignition of vapours.

Question 23

The bitumen grade for a pavement is selected mainly considering:

  1. the slope of the roadside side drains
  2. the shape of the aggregate particles alone
  3. the colour of the wearing course and markings
  4. climate and the traffic loading
Show answer & solution

Answer: (D) climate and the traffic loading

Harder grades suit hot climates and heavy traffic; softer grades suit cold climates.

Question 24

Cutback bitumen is:

  1. bitumen dispersed in water with an emulsifier
  2. bitumen mixed with Portland cement
  3. bitumen dissolved in a petroleum solvent
  4. a by-product of coal distillation
Show answer & solution

Answer: (C) bitumen dissolved in a petroleum solvent

The solvent evaporates (cures) after application, leaving the bitumen.

Question 25

Bitumen emulsion is:

  1. bitumen heated beyond its flash point before use
  2. bitumen blended with hydrated lime and sand
  3. bitumen dissolved in kerosene to lower its viscosity
  4. bitumen dispersed as droplets in water with an emulsifier
Show answer & solution

Answer: (D) bitumen dispersed as droplets in water with an emulsifier

Emulsions can be applied cold and break when the water leaves.

Question 26

The Marshall test is used for the:

  1. design of bituminous mixes by stability and flow
  2. design of cement concrete mixes by slump
  3. determination of the CBR of the subgrade soil
  4. measurement of the penetration of bitumen binders
Show answer & solution

Answer: (A) design of bituminous mixes by stability and flow

The Marshall method selects the optimum binder content for a mix.

Question 27

Quality control testing during highway construction is carried out mainly to:

  1. select the route alignment of the new road
  2. verify that the work meets the specifications
  3. fix the toll rates charged to road users
  4. forecast the future traffic growth on the road
Show answer & solution

Answer: (B) verify that the work meets the specifications

Testing during construction confirms that the as-built road meets the specifications.

Question 28

The layer of a flexible pavement placed directly on the subgrade is the:

  1. wearing course
  2. binder course
  3. sub-base course
  4. base course
Show answer & solution

Answer: (C) sub-base course

A flexible pavement sits on the subgrade, with the sub-base as its lowest layer.

Question 29

A typical flexible pavement, from the top downward, consists of:

  1. sub-base, wearing course, base course and subgrade
  2. base course, wearing course, subgrade and sub-base
  3. subgrade, sub-base, base course and wearing course
  4. wearing course, base course, sub-base and subgrade
Show answer & solution

Answer: (D) wearing course, base course, sub-base and subgrade

Layer quality and strength increase from the subgrade upward to the surface.

Question 30

The surface (wearing) course of a flexible pavement mainly provides:

  1. a smooth, durable, waterproof, skid-resistant surface
  2. the foundation support for all the layers
  3. the main drainage path for subgrade water
  4. the stopping space for emergency vehicles
Show answer & solution

Answer: (A) a smooth, durable, waterproof, skid-resistant surface

The wearing course resists traffic wear and weather and keeps water out of the lower layers.

Question 31

The base course of a flexible pavement mainly:

  1. drains the surface water away from the road
  2. provides the main structural strength and spreads loads
  3. acts as the natural ground beneath the road
  4. serves as the surface that is exposed to traffic
Show answer & solution

Answer: (B) provides the main structural strength and spreads loads

The base is the main load-spreading layer beneath the surfacing.

Question 32

A sub-base course mainly:

  1. supplies the skid resistance of the surface
  2. forms the wearing surface that is exposed to traffic
  3. gives extra support and spreads loads to the subgrade
  4. carries the road markings and reflective studs
Show answer & solution

Answer: (C) gives extra support and spreads loads to the subgrade

The sub-base spreads loads before they reach the subgrade and can serve as a drainage layer.

Question 33

A prime coat in flexible pavement construction is applied on:

  1. the natural subgrade soil directly beneath the road
  2. the joints of a cement concrete slab
  3. the top of a finished wearing course surface
  4. the prepared untreated granular base course
Show answer & solution

Answer: (D) the prepared untreated granular base course

Priming seals the granular base and binds loose particles before the bituminous layer is laid.

Question 34

Prime coats are commonly applied using:

  1. hydrated lime water sprayed from a tanker
  2. hot-mix asphalt concrete laid in a thin layer
  3. cutback bitumen or bitumen emulsion
  4. cement slurry mixed with sand and water
Show answer & solution

Answer: (C) cutback bitumen or bitumen emulsion

A low-viscosity binder is needed so that it penetrates the granular surface.

Question 35

A tack coat is applied when laying a new asphalt layer over:

  1. the natural sub-base soil layer
  2. an existing bituminous or concrete surface
  3. the earth shoulders beside the carriageway
  4. a raw untreated aggregate base course
Show answer & solution

Answer: (B) an existing bituminous or concrete surface

The tack coat is a thin bitumen film that bonds the new layer to the old one.

Question 36

A binder course lies between:

  1. the wearing course and the base course
  2. the shoulder of the road and the kerb
  3. the base course and the sub-base course
  4. the sub-base course and the subgrade
Show answer & solution

Answer: (A) the wearing course and the base course

In thicker bituminous pavements the binder course is the intermediate layer under the wearing course.

Question 37

Bituminous macadam generally involves:

  1. spreading dry stone with only water and then rolling it
  2. mixing coarse aggregate with bitumen, then spreading and compacting
  3. casting concrete slabs with joints between the slabs
  4. spraying binder and chips over an existing surface
Show answer & solution

Answer: (B) mixing coarse aggregate with bitumen, then spreading and compacting

BM is a bituminous mix of open to semi-dense grading used for base and binder courses.

Question 38

Dense Bituminous Macadam (DBM) is generally used for:

  1. very light rural tracks with few vehicles
  2. the wearing course of pedestrian footpaths
  3. the base or binder course under heavy traffic
  4. the shoulders of earth roads in dry areas
Show answer & solution

Answer: (C) the base or binder course under heavy traffic

DBM is a dense-graded, strong mix suited to structural layers.

Question 39

Compared with bituminous macadam, bituminous concrete (BC) is characterized by:

  1. a denser, well-graded mix with tighter quality control
  2. the absence of any bituminous binder in the mix
  3. an open-graded mix with practically no fine particles
  4. a composition identical to that of plain macadam
Show answer & solution

Answer: (A) a denser, well-graded mix with tighter quality control

BC is a high-quality dense-graded surfacing mix.

Question 40

Surface dressing (chip seal) generally involves:

  1. casting a concrete overlay on the old surface
  2. reconstructing the entire pavement structure in layers
  3. mixing the binder with soil in place using tillers
  4. spraying binder on the surface, then spreading and rolling chips
Show answer & solution

Answer: (D) spraying binder on the surface, then spreading and rolling chips

It renews the surface, seals cracks and improves skid resistance.

Question 41

Water Bound Macadam (WBM) construction involves:

  1. casting plain cement concrete slabs on the base
  2. compacting crushed stone with screenings and water
  3. spraying bitumen emulsion on the finished surface
  4. mixing aggregate with hot bitumen in a mixing plant
Show answer & solution

Answer: (B) compacting crushed stone with screenings and water

The binding action in WBM comes from stone interlock and the screenings, not from bitumen.

Question 42

Wet Mix Macadam (WMM) differs from WBM in that the aggregate and water are:

  1. added only after the rolling of the layer is complete
  2. replaced entirely by hot bitumen in a boiler
  3. pre-mixed in a plant before spreading and compacting
  4. mixed on the subgrade by hand with no control
Show answer & solution

Answer: (C) pre-mixed in a plant before spreading and compacting

Plant mixing gives better gradation and moisture control than WBM.

Question 43

The road-building method using layers of compacted, small, uniformly sized broken stone was introduced by:

  1. Pierre-Marie Tresaguet
  2. Thomas Telford
  3. Sher Shah Suri
  4. John Loudon McAdam
Show answer & solution

Answer: (D) John Loudon McAdam

Macadam's method used compacted layers of broken stone of small size, with no large-stone foundation.

Question 44

A grader (motor grader) is used mainly for:

  1. fine grading and levelling of subgrade or granular layers
  2. mixing hot bitumen with the aggregate at a plant
  3. hauling the aggregate from the quarry to the site
  4. compacting the pavement layers to the required density
Show answer & solution

Answer: (A) fine grading and levelling of subgrade or granular layers

A grader's blade shapes and levels surfaces to the required grade and cross-slope.

Question 45

Rollers (compactors) are used in highway construction mainly to:

  1. mix the bituminous materials uniformly
  2. compact the layers to the required density
  3. level the subgrade to the required grade
  4. spray the binder over the base course
Show answer & solution

Answer: (B) compact the layers to the required density

Adequate compaction gives strength and durability to each layer.

Question 46

A paver (asphalt or concrete paver) is used mainly to:

  1. mix the bituminous material at the hot-mix plant
  2. compact the finished layer to the specified density
  3. grade the subgrade to the correct level
  4. spread and screed the mix to the required thickness
Show answer & solution

Answer: (D) spread and screed the mix to the required thickness

A paver lays the mix uniformly to the correct level and thickness before the rollers compact it.

Question 47

The total thickness of a flexible pavement depends mainly on:

  1. subgrade strength (CBR), traffic and materials
  2. the width of the median and shoulders
  3. the number of side drains along the road
  4. the colour of the wearing course and markings
Show answer & solution

Answer: (A) subgrade strength (CBR), traffic and materials

Design thickness is chosen so that the stresses on each layer stay within its capacity.

Question 48

Bituminous mixes are best compacted:

  1. after the mix has cooled completely
  2. only on the following day of laying
  3. while the mix is still hot and workable
  4. before the tack coat is applied
Show answer & solution

Answer: (C) while the mix is still hot and workable

Compaction must be completed before the mix cools and becomes stiff.