What is the basic formula for hydroelectric power?

  1. P = mcΔT
  2. P = ρgQHη
  3. P = σT⁴
  4. P = VI only
Show answer & solution

Answer: (B) P = ρgQHη

Q is discharge, H is net head and η is overall efficiency.

Question 2

Which is the largest hydroelectric power station in Pakistan?

  1. Warsak
  2. Tarbela
  3. Ghazi Barotha
  4. Mangla
Show answer & solution

Answer: (B) Tarbela

Tarbela Dam is on the Indus River in Khyber Pakhtunkhwa.

Question 3

On which river is the Mangla Dam built?

  1. Chenab
  2. Indus
  3. Jhelum
  4. Kabul
Show answer & solution

Answer: (C) Jhelum

It is located in Azad Jammu and Kashmir.

Question 4

What type of hydropower project is Ghazi Barotha?

  1. A run-of-river project on the Indus that uses a power channel from a barrage
  2. A tidal power plant
  3. A storage dam on the Jhelum
  4. A pumped storage plant
Show answer & solution

Answer: (A) A run-of-river project on the Indus that uses a power channel from a barrage

It uses water released from Tarbela.

Question 5

On which river is the Warsak hydropower project located?

  1. Ravi River
  2. Jhelum River
  3. Indus River
  4. Kabul River
Show answer & solution

Answer: (D) Kabul River

It is near Peshawar.

Question 6

What is the Neelum–Jhelum hydropower project?

  1. A run-of-river project that diverts water of the Neelum River through a tunnel to the Jhelum
  2. A coal power plant
  3. A nuclear plant
  4. A solar park
Show answer & solution

Answer: (A) A run-of-river project that diverts water of the Neelum River through a tunnel to the Jhelum

It was completed in 2018.

Question 7

Which organisation is responsible for developing large hydropower projects in Pakistan?

  1. PSB
  2. NEPRA only
  3. WAPDA (Water and Power Development Authority)
  4. PAEC
Show answer & solution

Answer: (C) WAPDA (Water and Power Development Authority)

NEPRA is the electricity regulator.

Question 8

What is a run-of-river hydro plant?

  1. A pumped storage plant
  2. A plant with a large reservoir
  3. A plant that runs on coal
  4. A plant that uses river flow as it comes, with little or no storage
Show answer & solution

Answer: (D) A plant that uses river flow as it comes, with little or no storage

Its output varies with river flow.

Question 9

What is a pumped storage plant?

  1. A run-of-river plant
  2. A plant that pumps water to an upper reservoir during low demand and generates power during peak demand
  3. A thermal plant
  4. A tidal plant
Show answer & solution

Answer: (B) A plant that pumps water to an upper reservoir during low demand and generates power during peak demand

It works like a large battery for the grid.

Question 10

How are hydro plants classified by head?

  1. Low head, medium head and high head
  2. Base and peak only
  3. Coal, gas and oil
  4. Small, medium and large reservoirs only
Show answer & solution

Answer: (A) Low head, medium head and high head

Low-head plants use Kaplan turbines and high-head plants Pelton wheels.

Question 11

Which turbine is suitable for a high-head hydro plant (above about 300 m)?

  1. Bulb turbine
  2. Kaplan turbine
  3. Propeller turbine
  4. Pelton wheel
Show answer & solution

Answer: (D) Pelton wheel

Impulse turbines suit high heads and low flows.

Question 12

Which turbine is suitable for a low-head hydro plant with large discharge?

  1. Turgo wheel
  2. Pelton wheel
  3. Kaplan turbine
  4. Steam turbine
Show answer & solution

Answer: (C) Kaplan turbine

Kaplan turbines have adjustable blades.

Question 13

Which turbine is suitable for medium heads?

  1. Pelton wheel
  2. Francis turbine
  3. Kaplan turbine only
  4. Steam turbine
Show answer & solution

Answer: (B) Francis turbine

Tarbela and Mangla use Francis turbines.

Question 14

What is the function of a spillway in a dam?

  1. To generate electricity
  2. To store sediment
  3. To carry water to turbines
  4. To pass surplus flood water safely downstream
Show answer & solution

Answer: (D) To pass surplus flood water safely downstream

Spillways protect the dam from overtopping.

Question 15

What is the function of a penstock?

  1. To carry water under pressure from the reservoir or forebay to the turbines
  2. To store water
  3. To carry water away from turbines
  4. To spill flood water
Show answer & solution

Answer: (A) To carry water under pressure from the reservoir or forebay to the turbines

It must withstand water hammer pressures.

Question 16

What is the function of a surge tank?

  1. To measure flow
  2. To store fuel
  3. To reduce water hammer and absorb sudden pressure changes when turbine load changes
  4. To generate electricity
Show answer & solution

Answer: (C) To reduce water hammer and absorb sudden pressure changes when turbine load changes

It is placed between the tunnel and penstock.

Question 17

What is the function of a draft tube in a hydro plant?

  1. To store water
  2. To recover kinetic energy from water leaving a reaction turbine and allow the turbine to be set above tailwater
  3. To carry water to the turbine
  4. To spill flood water
Show answer & solution

Answer: (B) To recover kinetic energy from water leaving a reaction turbine and allow the turbine to be set above tailwater

It is used with Francis and Kaplan turbines.

Question 18

What is the tailrace?

  1. The spillway
  2. The channel to the turbines
  3. The channel that carries water away from the power house after it leaves the turbines
  4. The reservoir
Show answer & solution

Answer: (C) The channel that carries water away from the power house after it leaves the turbines

Tailwater level affects net head.

Question 19

What are the main advantages of hydroelectric power?

  1. No fuel cost, low running cost, quick starting and long plant life
  2. No environmental effects at all
  3. Low capital cost
  4. No dependence on rainfall
Show answer & solution

Answer: (A) No fuel cost, low running cost, quick starting and long plant life

Hydro plants are ideal for meeting peak loads.

Question 20

What are the main disadvantages of hydroelectric power?

  1. Slow starting
  2. Short life
  3. High fuel cost
  4. High capital cost, long construction time, dependence on rainfall and sedimentation of reservoirs
Show answer & solution

Answer: (D) High capital cost, long construction time, dependence on rainfall and sedimentation of reservoirs

Siltation reduces the storage of Tarbela and Mangla over time.

Question 21

What is a hydrograph?

  1. A graph of head against efficiency
  2. A graph showing river discharge against time
  3. A graph of rainfall against temperature
  4. A graph of power against speed
Show answer & solution

Answer: (B) A graph showing river discharge against time

It is used to plan reservoir and plant capacity.

Question 22

What is a flow duration curve?

  1. A graph of turbine speed
  2. A graph of power output against time
  3. A curve showing the percentage of time that river flow equals or exceeds given values
  4. A graph of flow against head
Show answer & solution

Answer: (C) A curve showing the percentage of time that river flow equals or exceeds given values

It helps decide firm power and installed capacity.

Question 23

What is a mass curve used for in hydro planning?

  1. Finding generator size
  2. Finding turbine efficiency
  3. Finding power factor
  4. Finding the reservoir storage needed to provide a given regulated flow
Show answer & solution

Answer: (D) Finding the reservoir storage needed to provide a given regulated flow

It plots cumulative flow against time.

Question 24

What is the gross head of a hydro plant?

  1. The difference between headwater level and tailwater level
  2. The head lost in the penstock
  3. The net head after losses
  4. The height of the dam only
Show answer & solution

Answer: (A) The difference between headwater level and tailwater level

Net head = gross head − losses.

Question 25

Why are hydro plants suitable for peak load supply?

  1. They take days to start
  2. They can start, stop and change load very quickly
  3. They work only at base load
  4. They cannot change load
Show answer & solution

Answer: (B) They can start, stop and change load very quickly

Storage hydro plants follow demand easily.

Question 26

What is the net head of a hydro plant?

  1. The gross head plus losses
  2. The tailwater depth
  3. The gross head minus head losses in the intake, tunnel and penstock
  4. The height of the dam
Show answer & solution

Answer: (C) The gross head minus head losses in the intake, tunnel and penstock

Turbines are rated on net head.

Question 27

What is an intake structure in a hydro plant?

  1. The power house
  2. The tailrace
  3. The spillway
  4. The entry point where water is drawn from the reservoir into the tunnel or penstock
Show answer & solution

Answer: (D) The entry point where water is drawn from the reservoir into the tunnel or penstock

Trash racks keep debris out of the intake.

Question 28

What is the function of a trash rack?

  1. To prevent floating debris from entering the turbines
  2. To control speed
  3. To measure flow
  4. To spill flood water
Show answer & solution

Answer: (A) To prevent floating debris from entering the turbines

It is placed at the intake.

Question 29

What is a forebay?

  1. The main reservoir
  2. A small pond at the end of a power canal that supplies water steadily to the penstocks
  3. The tailrace
  4. The spillway
Show answer & solution

Answer: (B) A small pond at the end of a power canal that supplies water steadily to the penstocks

It acts as a small regulating reservoir.

Question 30

Why is siltation a serious problem for dams in Pakistan?

  1. It increases storage
  2. It improves turbine efficiency
  3. It has no effect
  4. Heavy sediment loads in rivers like the Indus reduce reservoir storage capacity over time
Show answer & solution

Answer: (D) Heavy sediment loads in rivers like the Indus reduce reservoir storage capacity over time

Sediment management is important for Tarbela.

Question 31

What is the main purpose of Tarbela and Mangla dams apart from power generation?

  1. Navigation only
  2. Storing water for irrigation and controlling floods
  3. Fishing only
  4. Mining
Show answer & solution

Answer: (B) Storing water for irrigation and controlling floods

They are multipurpose projects.

Question 32

What is mini or micro hydro power?

  1. Pumped storage only
  2. Tidal plants
  3. Small hydro plants, often run-of-river, supplying local communities
  4. Very large dams
Show answer & solution

Answer: (C) Small hydro plants, often run-of-river, supplying local communities

They are common in the northern areas of Pakistan.

Question 33

What is the specific speed of a turbine used for in hydro plant design?

  1. Selecting the type of turbine suited to the available head and discharge
  2. Calculating generator voltage
  3. Calculating dam height
  4. Calculating reservoir size
Show answer & solution

Answer: (A) Selecting the type of turbine suited to the available head and discharge

Low specific speed suits Pelton and high specific speed suits Kaplan.

Practice these 33 questions interactively →