What is a fixed cost in mining?
Show answer & solution
Answer: (B) A cost that does not change with the level of production in the short term
Examples include salaries of staff, insurance and lease rentals.
Mining Engineering · Mine Economics & Mineral Processing
28 questions, each with the answer and a worked solution.
Practice interactively and track your score →What is a fixed cost in mining?
Answer: (B) A cost that does not change with the level of production in the short term
Examples include salaries of staff, insurance and lease rentals.
What is a variable cost in mining?
Answer: (C) A cost that changes with the level of production
Fuel, explosives and power are variable costs.
How is unit operating cost usually expressed in mining?
Answer: (A) Cost per tonne mined or per tonne of ore processed
Unit costs allow comparison between periods and mines.
What is an overhead (indirect) cost?
Answer: (B) A cost not directly tied to a single production activity, such as administration
Overheads are allocated to cost centres.
What are owning costs of mining equipment?
Answer: (D) Depreciation, interest, insurance and taxes related to owning the machine
Operating costs include fuel, tyres, repairs and labour.
Using straight-line depreciation, what is the annual depreciation of a machine costing Rs 10 million with a salvage value of Rs 2 million and a life of 8 years?
Answer: (C) Rs 1 million
(10 − 2)/8 = Rs 1 million per year.
What is declining balance depreciation?
Answer: (D) A method charging a fixed percentage of the remaining book value each year
It gives larger charges in early years.
What does economy of scale mean in mining?
Answer: (A) Unit costs fall as the scale of production increases
Large equipment and plants spread fixed costs over more tonnes.
How is the break-even production quantity calculated?
Answer: (B) Fixed cost divided by (price per unit − variable cost per unit)
At break-even, total revenue equals total cost.
What is the break-even production if fixed costs are Rs 10 million per year, price is Rs 5,000 per tonne and variable cost is Rs 3,000 per tonne?
Answer: (C) 5,000 tonnes per year
10,000,000/(5,000 − 3,000) = 5,000 t.
What is contribution margin?
Answer: (B) Price per unit minus variable cost per unit
Contribution margin pays fixed costs and then gives profit.
What does OMS (output per man-shift) measure?
Answer: (D) Labour productivity
OMS is a common productivity measure in coal mining.
What is contract mining?
Answer: (A) Mining work carried out by a specialist contractor for the mine owner
Contractors may supply equipment and labour for drilling, loading or hauling.
What is the "six-tenths rule" in mining cost estimation?
Answer: (D) Capital cost of a plant varies with capacity raised to the power of about 0.6
Cost2 = Cost1 × (Capacity2/Capacity1)^0.6.
By the six-tenths rule, about how much would a plant cost if its capacity is doubled from a plant costing Rs 100 million?
Answer: (B) About Rs 152 million
100 × 2^0.6 ≈ 152.
What is all-in sustaining cost (AISC) in gold mining?
Answer: (A) A cost measure including operating costs plus sustaining capital and related costs per ounce
AISC gives a fuller picture than cash cost alone.
What is the cash operating cost of a mine?
Answer: (C) Direct cash costs of mining, processing and site administration
Cash costs exclude non-cash items such as depreciation.
What is life-cycle costing of equipment?
Answer: (B) Considering all costs of a machine over its entire life, including purchase, operation, maintenance and disposal
It helps choose equipment with the lowest total cost.
When is equipment usually replaced in economic terms?
Answer: (C) When its average cost per hour starts to rise because of increasing repair costs
Replacement analysis compares keeping and replacing options.
What is a cost centre in mine accounting?
Answer: (D) An area or activity, such as drilling or hauling, to which costs are collected
Cost centres help control and compare costs.
Which cost usually forms the largest share of operating cost in open pit mines?
Answer: (A) Loading and hauling
Truck haulage cost rises as pits deepen.
What is a mining budget?
Answer: (A) A financial plan of expected production, costs and capital for a period
Actual results are compared with the budget each month.
What is the purpose of variance analysis in mine costing?
Answer: (B) To explain differences between actual and budgeted costs
It identifies where costs are out of control.
What is capital intensity of a mine?
Answer: (D) The amount of capital required per unit of production capacity
Highly mechanised mines are capital intensive.
What is the main benefit of preventive maintenance for mining equipment?
Answer: (C) It reduces breakdowns and overall repair cost
Planned servicing improves availability and reliability.
Which cost is usually larger per tonne in underground mining than in open pit mining?
Answer: (D) Mining cost per tonne
Underground methods have higher development and support costs per tonne.
What is sunk cost?
Answer: (A) A cost already spent that cannot be recovered and should not affect future decisions
Decisions should be based on future cash flows.
What is cost per tonne of ore if total annual operating cost is Rs 600 million and 2 million tonnes of ore are produced?
Answer: (B) Rs 300 per tonne
600,000,000/2,000,000 = Rs 300/t.