Question 1
The primary objective of surveying is to
- test the strength and quality of the materials used in construction
- estimate the quantities and costs of a proposed construction project
- prepare structural designs for buildings, bridges, dams and other engineering works
- fix the relative positions of points on, above or below the earth's surface
Show answer & solution
Answer: (D) fix the relative positions of points on, above or below the earth's surface
Surveying determines the relative positions of points and features so that they can be mapped or set out.
Question 2
Based on whether the curvature of the earth is taken into account, surveying is broadly classified into
- land surveying and hydrographic surveying
- chain surveying and compass surveying
- plane surveying and geodetic surveying
- cadastral surveying and topographic surveying
Show answer & solution
Answer: (C) plane surveying and geodetic surveying
Plane surveying treats the earth as flat, while geodetic surveying allows for its curvature.
Question 3
In plane surveying, the curvature of the earth is
- allowed for in the angular measurements but ignored in the distances
- neglected, the reference surface being treated as a horizontal plane
- applied as a correction to every measured horizontal distance
- measured as the main quantity of the survey and then adjusted
Show answer & solution
Answer: (B) neglected, the reference surface being treated as a horizontal plane
Over small areas the difference between the spherical and plane surface is negligible, so plane surveying ignores curvature.
Question 4
Geodetic surveying is generally employed for
- the setting out of foundations for individual buildings on a construction site
- small areas of a few square kilometres, where the ground may be treated as a plane surface
- large areas, such as national control networks, where the curvature of the earth is allowed for
- the mapping of small plots and field boundaries by chain and offsets
Show answer & solution
Answer: (C) large areas, such as national control networks, where the curvature of the earth is allowed for
Over extensive areas the earth's curvature affects distances and angles, so geodetic methods are needed for accuracy.
Question 5
The principle of working from the whole to the part in surveying means that
- the smallest features are surveyed first and combined into larger units to form the map
- the survey starts from any arbitrary station and adds new stations one after another
- a framework of accurate control points is fixed first and the details are then surveyed within it
- the details are surveyed first, and control points are chosen afterwards to fit the surveyed details
Show answer & solution
Answer: (C) a framework of accurate control points is fixed first and the details are then surveyed within it
Establishing accurate control first prevents errors from accumulating and being magnified when the details are added.
Question 6
The second fundamental principle of surveying is to
- measure all the angles of a figure and avoid any measurement of distances
- locate a new point by at least two independent measurements from fixed reference points
- fix each new point by a single, very precise measurement from the previous point
- accept the first measurement of a quantity without an independent check
Show answer & solution
Answer: (B) locate a new point by at least two independent measurements from fixed reference points
Fixing a point by two independent measurements gives a check against mistakes.
Question 7
The scale of a map is the ratio of
- the area of the map sheet to the area of the ground surveyed
- the contour interval to the horizontal equivalent of the slope
- a distance measured on the map to the corresponding distance on the ground
- a distance measured on the ground to the corresponding distance on the map
Show answer & solution
Answer: (C) a distance measured on the map to the corresponding distance on the ground
Map scale is map distance : ground distance, for example 1:1000 means 1 unit on the map represents 1000 units on the ground.
Question 8
Compared with a small-scale map such as 1:50 000, a large-scale map such as 1:500 shows
- a smaller ground area, but with more detail
- a larger ground area, with the same amount of detail
- a larger ground area, but with less detail
- a smaller ground area, with less detail
Show answer & solution
Answer: (A) a smaller ground area, but with more detail
A larger scale fraction (1/500 > 1/50 000) magnifies the ground, so less area is covered on the sheet but features are shown in finer detail.
Question 9
Which of the following is the largest map scale?
- 1:500
- 1:5 000
- 1:50 000
- 1:500 000
Show answer & solution
Answer: (A) 1:500
The largest scale has the smallest denominator, so 1:500 (the fraction 1/500) is larger than the other scales.
Question 10
Conventional signs on a topographic map are used to
- give the elevations of points that lie between the contour lines
- represent natural and man-made features in a standard, easily recognised way
- show the survey stations and the closing error of the control traverse
- indicate the scale, orientation and projection of the map sheet and its borders
Show answer & solution
Answer: (B) represent natural and man-made features in a standard, easily recognised way
Standard symbols and colours let any reader identify roads, buildings, rivers, vegetation and similar features.
Question 11
The national geodetic control network maintained by the Survey of Pakistan, consisting of triangulation stations and bench marks, provides
- reference marks whose values have to be re-determined by every user before each survey
- a nationally consistent framework of precisely known coordinates and elevations for tying local surveys
- a reference grid for compass traverses, which cannot be used for levelling or triangulation
- local reference points whose positions and heights are assumed afresh for each separate project and not related to each other
Show answer & solution
Answer: (B) a nationally consistent framework of precisely known coordinates and elevations for tying local surveys
National control points give all surveys a common, precise coordinate and height reference.
Question 12
A control survey network for a large engineering project such as a highway or dam is important because it
- fixes the final design levels and alignment of the proposed works for the contractor
- makes any further surveying unnecessary once construction has started on the project site
- gives fixed reference points for detail surveys and setting out, limiting error build-up
- replaces the topographic survey of the site by a small set of spot heights at key points
Show answer & solution
Answer: (C) gives fixed reference points for detail surveys and setting out, limiting error build-up
All detail surveys and setting-out are tied to the same control, which keeps the work consistent across the project.
Question 13
Hydrographic surveying is the branch of surveying concerned with the mapping of
- the heights of mountain peaks and ridges above mean sea level
- the boundaries of agricultural land holdings and the ownership of each parcel
- water bodies such as rivers, lakes and coastal waters, including their depths
- underground utilities such as buried pipelines, cables and drains beneath roads
Show answer & solution
Answer: (C) water bodies such as rivers, lakes and coastal waters, including their depths
Hydrographic surveys map shorelines and underwater features, and record depths by soundings.
Question 14
In hydrographic surveying, sounding means
- fixing the position of the shoreline by chaining along it at regular intervals
- measuring the depth of water at selected points of a water body
- measuring the velocity of flow at a river cross-section with a current meter
- measuring the slope of the water surface between two gauges
Show answer & solution
Answer: (B) measuring the depth of water at selected points of a water body
Soundings are depth measurements at a series of fixed positions, from which the bed profile is drawn.
Question 15
Setting out a survey, as distinct from surveying existing features, means
- adjusting the closing error of a traverse after the fieldwork is finished
- computing the area of an existing plot from field measurements and coordinates
- recording the existing features of the ground and plotting them on a plan to scale
- marking the positions of a proposed design, such as building corners, on the ground
Show answer & solution
Answer: (D) marking the positions of a proposed design, such as building corners, on the ground
Setting out transfers a design from the drawings to the ground, the reverse of ordinary surveying.
Question 16
Marking the centreline of a proposed road on the ground from design coordinates, using a total station, is an application of
- construction surveying
- cadastral surveying of property boundaries
- topographic surveying of existing features
- hydrographic surveying of water bodies
Show answer & solution
Answer: (A) construction surveying
Laying out a design alignment on site is a typical construction surveying task.
Question 17
Which of the following pairs consists only of classical (non-electronic) surveying instruments?
- LiDAR scanner and drone
- total station and GNSS receiver
- chain and plane table
- digital level and robotic total station
Show answer & solution
Answer: (C) chain and plane table
The chain and plane table are traditional instruments, while the others are electronic or satellite-based modern equipment.
Question 18
By their nature, errors in surveying measurements are classified as
- field errors and office errors, according to where they arise
- mistakes (blunders), systematic errors and random errors
- positive errors, negative errors and zero errors
- large errors and small errors, according to their magnitude
Show answer & solution
Answer: (B) mistakes (blunders), systematic errors and random errors
The standard classification is gross mistakes, systematic (cumulative) errors and random (accidental) errors, each treated differently.
Question 19
A mistake (blunder) in surveying, such as misreading a staff or transposing digits, is
- an error from changing temperature that accumulates with the number of measurements
- an error from a defective instrument that repeats in the same sense every time it is used
- a small unavoidable error that follows the laws of probability and can be reduced by averaging
- a gross error from carelessness, which must be detected by checks and eliminated
Show answer & solution
Answer: (D) a gross error from carelessness, which must be detected by checks and eliminated
Blunders are human lapses that cannot be adjusted away; they must be found by checking and the measurement repeated.
Question 20
A systematic (cumulative) error in surveying is one that
- arises from carelessness in reading and is removed by repeating the reading carefully
- tends to be reduced by taking the mean of a large number of observations
- is equally likely to be positive or negative and tends to cancel over many measurements
- follows a definite law and accumulates in the same sense, as with a tape of wrong length
Show answer & solution
Answer: (D) follows a definite law and accumulates in the same sense, as with a tape of wrong length
Systematic errors keep the same sign and add up, so they must be removed by calibration or by applying a correction.
Question 21
A random (accidental) error in surveying is one that
- is caused by an incorrectly calibrated instrument and can be removed by a formula or correction
- has no definite pattern, is equally likely to be positive or negative, and follows probability
- always has the same sign and accumulates with the number of observations made
- is a gross error that can be found by a check measurement and then removed
Show answer & solution
Answer: (B) has no definite pattern, is equally likely to be positive or negative, and follows probability
Random errors are small, unpredictable variations in observation, treated by statistical methods such as averaging.
Question 22
For several equally reliable observations of a quantity affected only by random errors, the most probable value is
- the observation that has been repeated most often
- the square root of the mean of the squares of the observations
- the mid-value between the largest and the smallest observation
- the sum of the observations divided by their number
Show answer & solution
Answer: (D) the sum of the observations divided by their number
The arithmetic mean is the most probable value for equal-weight observations containing only random errors.
Question 23
In the adjustment of observations, weights are generally assigned so that
- more reliable observations, such as a mean of more repetitions, get greater weight
- the latest observation gets the greatest weight whatever its quality
- all observations get the same weight, because they were made with the same instrument and procedure
- observations of larger numerical value get greater weight
Show answer & solution
Answer: (A) more reliable observations, such as a mean of more repetitions, get greater weight
A weight expresses the relative reliability of an observation, so better data influence the adjusted result more.
Question 24
Standard deviation and probable error are used in surveying to
- express the precision, that is the expected size of random errors, of a set of observations
- give the true value of the measured quantity from a single observation
- locate and eliminate the blunders in a set of observations by comparison with the mean
- remove the systematic errors from a set of observations before the mean is taken
Show answer & solution
Answer: (A) express the precision, that is the expected size of random errors, of a set of observations
These statistical measures quantify the scatter of observations about their mean and so describe precision.
Question 25
The method of least squares is used in the adjustment of surveys to
- reject every observation that does not satisfy the geometric conditions of the figure exactly
- share the misclosure equally among all observations whatever their weights
- reduce the number of observations required to fix a network
- adjust redundant observations so that the sum of squares of the residuals is a minimum
Show answer & solution
Answer: (D) adjust redundant observations so that the sum of squares of the residuals is a minimum
Least squares gives the most probable adjusted values by minimising the sum of weighted squared residuals.
Question 26
Redundant observations in a survey are valuable mainly because they
- allow errors to be checked and a rigorous adjustment such as least squares to be made
- make the computations simpler and shorter by reducing the number of equations to be solved
- remove the systematic errors automatically without any correction
- are needed only when satellite positioning or EDM is used for the survey
Show answer & solution
Answer: (A) allow errors to be checked and a rigorous adjustment such as least squares to be made
Extra observations beyond the minimum give checks on mistakes and the data for a statistically sound adjustment.