Cross-drainage works are needed where

  1. a canal has to cross a natural drainage channel
  2. a canal takes off from a river at a diversion headwork
  3. two canals of different ranks meet and merge at a junction
  4. a distributary ends at its tail outlet in the command area
Show answer & solution

Answer: (A) a canal has to cross a natural drainage channel

They carry the canal and the drainage across each other without mixing in a harmful way.

Question 2

A plain aqueduct is provided where

  1. the drainage HFL is below the canal bed, so the canal crosses over in a trough
  2. the canal and drainage are at the same level and are allowed to mix freely
  3. the drainage HFL is above the canal bed and flows through barrels under the canal
  4. the canal bed lies below the drainage bed, so the canal passes under the drainage
Show answer & solution

Answer: (A) the drainage HFL is below the canal bed, so the canal crosses over in a trough

In an aqueduct the canal is carried above the drainage.

Question 3

A super-passage is a cross-drainage work in which

  1. the canal runs full, under pressure, through barrels beneath the drainage bed, with the drainage above
  2. the drainage is admitted into the canal at an inlet and leaves it again at an outlet downstream
  3. the canal is carried over the drainage in a masonry trough
  4. the canal flows with a free surface beneath a drainage whose bed is above the canal full supply level
Show answer & solution

Answer: (D) the canal flows with a free surface beneath a drainage whose bed is above the canal full supply level

A super-passage is the reverse of an aqueduct: the drainage flows over the canal.

Question 4

A canal siphon is a cross-drainage work in which

  1. the canal flows under pressure through barrels below the drainage bed
  2. the canal is carried in a trough above a drainage whose HFL is below the canal bed
  3. the canal and drainage meet at the same level, with regulators controlling the combined flow
  4. the drainage is admitted into the canal at an inlet and leaves it at an outlet
Show answer & solution

Answer: (A) the canal flows under pressure through barrels below the drainage bed

When the drainage lies above the canal and the canal bed is below its level, the canal is siphoned beneath.

Question 5

A level crossing is a cross-drainage arrangement in which

  1. the canal passes under the drainage in a closed barrel with pressure flow
  2. the canal and drainage meet at one level and regulators control the flow
  3. the drainage is carried to the tail of the canal and disposed of in an escape
  4. the canal passes over the drainage in a masonry trough built across the stream
Show answer & solution

Answer: (B) the canal and drainage meet at one level and regulators control the flow

Level crossings suit small drainages where the two flows can be combined and regulated.

Question 6

An inlet-outlet arrangement is used for very minor drainage, in which

  1. the canal discharge is diverted into the drainage permanently at the crossing point
  2. the canal is carried in a trough above the minor drainage channel
  3. the drainage enters the canal at an inlet and leaves downstream at an outlet
  4. the drainage is dammed and stored upstream of the canal bank
Show answer & solution

Answer: (C) the drainage enters the canal at an inlet and leaves downstream at an outlet

A short length of canal itself carries the small drainage flow.

Question 7

The type of cross-drainage work at a site is selected mainly according to the

  1. length of the canal reach and the type of lining used in it
  2. relative levels of canal bed and FSL and the drainage bed and HFL
  3. silt factor of the canal soil and the grade of the bed material
  4. cropping pattern and the intensity of irrigation in the command area
Show answer & solution

Answer: (B) relative levels of canal bed and FSL and the drainage bed and HFL

Relative levels decide between aqueduct, super-passage, siphon or level crossing.

Question 8

Cross-drainage works generally form

  1. an optional item that can be omitted in any alignment chosen
  2. a minor item of cost, needing little design attention at most of the sites
  3. a cheap standard item that is copied unchanged at every site visited
  4. a costly item needing careful hydraulic and structural design
Show answer & solution

Answer: (D) a costly item needing careful hydraulic and structural design

Two flow systems interact at the crossing, so these are among the costliest canal structures.

Question 9

The design discharge of the drainage at a cross-drainage work is based on the

  1. full supply discharge of the canal, increased by a suitable safety factor
  2. flood discharge from the drainage's own catchment and flood frequency
  3. average of the canal discharge and the drainage discharge
  4. standard value adopted for all the structures of the canal system
Show answer & solution

Answer: (B) flood discharge from the drainage's own catchment and flood frequency

The drainage flood is independent of the canal discharge.

Question 10

The afflux caused by a cross-drainage structure on the natural drainage is kept small mainly to

  1. increase the scour depth downstream
  2. raise the full supply level of the canal
  3. avoid excessive flooding and backwater upstream
  4. increase the discharge capacity of the drainage
Show answer & solution

Answer: (C) avoid excessive flooding and backwater upstream

Excessive afflux submerges land and property upstream of the structure.

Question 11

Falls, regulators, escapes, outlets and cross-drainage works are provided on a canal system because

  1. the structures increase seepage so that the groundwater is recharged
  2. Lacey's theory requires the structures in order to compute the silt factor of the canal
  3. a plain channel cannot be built on alluvial soil without such structures in the system
  4. a plain channel alone cannot convey, control and distribute water or cross obstacles
Show answer & solution

Answer: (D) a plain channel alone cannot convey, control and distribute water or cross obstacles

A working canal system needs a range of ancillary structures, each with its own function.

Question 12

River training works near a headwork are provided mainly to

  1. guide and confine the flow through the waterway and protect banks
  2. raise the river bed level so as to increase the pond level at the headworks
  3. enlarge the meander belt so that the river spreads across its floodplain
  4. store flood volume behind the structure to supply the canal in the dry months
Show answer & solution

Answer: (A) guide and confine the flow through the waterway and protect banks

Guide banks, bunds and bank protection keep the river on a stable course through the structure.

Question 13

Guide banks at a barrage are aligned so as to

  1. direct the flow squarely through the waterway and prevent outflanking
  2. line the canal banks near the head regulator
  3. project into the flow at an angle to deflect the current to the opposite bank
  4. run across the full width of the river to hold the pond
Show answer & solution

Answer: (A) direct the flow squarely through the waterway and prevent outflanking

Guide banks run roughly parallel to the desired flow, unlike spurs that project into it.

Question 14

Meander length and meander belt describe the

  1. depth of scour below the pond level at the headworks, in a flood
  2. fixed width of the canal cross-section at the design discharge
  3. length of the guide bank upstream of the axis of the barrage
  4. natural windings of a river, which guide the spacing of training works
Show answer & solution

Answer: (D) natural windings of a river, which guide the spacing of training works

Training works should work with the river's natural meandering behaviour.

Question 15

A spur (groyne) is a structure

  1. projecting from the bank into the river to deflect the current from the bank
  2. buried in the bank with no projection into the stream at any level
  3. laid parallel to the bank so as to line its slope and keep the flow away
  4. built across the full width of the river to raise its water level
Show answer & solution

Answer: (A) projecting from the bank into the river to deflect the current from the bank

Spurs deflect flow and induce silting in their lee.

Question 16

Revetment (pitching) of a river bank consists of

  1. a cut channel across a meander loop that shortens the river
  2. a protective cover of stone or concrete blocks laid over the bank surface
  3. a projection into the stream that deflects the current away from the bank
  4. a flood embankment set back from the river bank on the floodplain
Show answer & solution

Answer: (B) a protective cover of stone or concrete blocks laid over the bank surface

Revetment armours the bank directly against erosion.

Question 17

A cutoff on a meandering river is made by

  1. constructing a channel that bypasses the barrage in the flood season
  2. building a wall across the river to hold the pond
  3. lengthening the river by digging additional loops on its course
  4. shortening the river by a new channel across a meander loop
Show answer & solution

Answer: (D) shortening the river by a new channel across a meander loop

Cutoffs shorten the course, helping flood conveyance or navigation.

Question 18

Bio-engineering (vegetative) measures on river banks

  1. can complement structural works by stabilising slopes
  2. are used only on lined canals
  3. give no protection against erosion
  4. are sufficient alone to hold banks against high flood velocities
Show answer & solution

Answer: (A) can complement structural works by stabilising slopes

Vegetation adds stability and environmental benefit alongside structural measures.

Question 19

River morphology is important in river training design because

  1. morphology affects only the design of the canal lining downstream of the headwork
  2. all rivers behave alike, so a standard layout suits any site
  3. training works must suit the river's present and likely future pattern
  4. a river's pattern never changes, so site studies of its behaviour are unnecessary
Show answer & solution

Answer: (C) training works must suit the river's present and likely future pattern

Design should reflect the river's present and probable future behaviour.

Question 20

A braided river reach, with many shifting channels, presents

  1. greater difficulty in training and siting structures as channels shift often
  2. easier siting, since flow is spread over many shallow channels
  3. no problem at all, since braided rivers carry very little sediment through the reach
  4. lower afflux because of the multiple channels across the river
Show answer & solution

Answer: (A) greater difficulty in training and siting structures as channels shift often

Frequent shifting makes braided reaches harder to control.

Question 21

Successful river training requires

  1. vegetation measures used alone on every river, with no structures of any kind
  2. a standard design adopted unchanged from a nearby river with a similar flow
  3. site-specific knowledge of flow, sediment and morphology plus sound structural design
  4. heavy structures that fully resist the river instead of guiding it
Show answer & solution

Answer: (C) site-specific knowledge of flow, sediment and morphology plus sound structural design

A one-size-fits-all approach does not work.

Question 22

A diversion headwork, such as the Sukkur Barrage on the Indus, is mainly meant to

  1. generate hydroelectric power as the main aim of the structure on the river
  2. detain floods so as to protect the downstream reach from inundation by the river
  3. store flood volume for use over several years of low flow
  4. raise the river level to divert flow into canals without large storage
Show answer & solution

Answer: (D) raise the river level to divert flow into canals without large storage

A headwork diverts flow and, unlike a storage dam, creates little storage.

Question 23

The pond level at a diversion headwork is fixed to

  1. give enough head to divert the design discharge through the head regulator
  2. equal the downstream bed level of the river below the weir axis
  3. keep the river at its natural level for the navigation of boats and barges
  4. equal the maximum flood level of the river at the site
Show answer & solution

Answer: (A) give enough head to divert the design discharge through the head regulator

The pond must command the canal head to deliver the required discharge.

Question 24

The site of a diversion headwork is chosen mainly for

  1. the confluence of the largest tributary, regardless of the foundation conditions
  2. the widest and most braided reach of the river on the plains
  3. a stable channel, sound foundation and enough level to command the area
  4. a reach with the steepest bed slope along the whole river
Show answer & solution

Answer: (C) a stable channel, sound foundation and enough level to command the area

Stability, foundation and commanding elevation drive site selection.

Question 25

Compared with a barrage, a weir is characterised by

  1. storage of floods in a large reservoir for several years
  2. a body of earth embankment spanning the whole valley
  3. a fixed crest raising the level, with little or no gate control
  4. large gates over most of its length for the regulation of floods
Show answer & solution

Answer: (C) a fixed crest raising the level, with little or no gate control

A weir raises the level mainly by its crest, whereas a barrage uses gates.

Question 26

The undersluices of a headwork serve to

  1. admit the silt-laden water directly into the canal off-take at all stages
  2. divert most of the flood flow into the canal through its head regulator
  3. keep a deep scoured channel near the head regulator and flush silt so clearer water enters
  4. store water for the dry season behind the barrage
Show answer & solution

Answer: (C) keep a deep scoured channel near the head regulator and flush silt so clearer water enters

Undersluices maintain a deep approach channel to the head regulator.

Question 27

A silt excluder is provided to

  1. admit the silt-laden bottom layer into the canal in preference to the top layer
  2. raise the pond level by retaining the sediment upstream
  3. remove the bottom sediment before the water enters the head regulator, through tunnels
  4. mix the sediment evenly through the depth of flow in the pond upstream
Show answer & solution

Answer: (C) remove the bottom sediment before the water enters the head regulator, through tunnels

Bottom layers rich in sediment are passed to the river, so cleaner top water enters the canal.

Question 28

A fish ladder at a barrage is provided to

  1. prevent scour in front of the head regulator
  2. dissipate the energy of the water below the barrage
  3. let migratory fish pass the barrage
  4. measure the discharge through the gates
Show answer & solution

Answer: (C) let migratory fish pass the barrage

It reduces an ecological impact of the barrage.

Question 29

The design flood of a diversion headwork is estimated from

  1. the full supply discharge of the canal, with an added margin for safety
  2. the highest flood recorded during the last year only, plus a small margin
  3. flood frequency analysis suited to the structure's importance and design life
  4. the mean annual flow of the river at the site, with some margin added
Show answer & solution

Answer: (C) flood frequency analysis suited to the structure's importance and design life

A conservative design flood ensures safety against major floods.

Question 30

A launching apron near a headwork provides

  1. flexible stone protection that launches into any scour hole
  2. a sheet-pile line that cuts off the seepage under the floor
  3. a drainage filter laid beneath the floor of the barrage
  4. a rigid concrete slab that never moves with the bed
Show answer & solution

Answer: (A) flexible stone protection that launches into any scour hole

The loose stone settles into the scour hole and keeps protecting the foundation.