Question 1
Reservoir sedimentation is more severe in catchments with
- gentle slopes covered by permanent grass that holds the soil
- heavy erosion from deforestation, overgrazing and poor land use
- mostly bare rock with very little soil material available to erode
- dense forest cover and well-maintained terraced slopes with little erosion
Show answer & solution
Answer: (B) heavy erosion from deforestation, overgrazing and poor land use
Eroded soils deliver more sediment to the reservoir.
Question 2
Catchment area treatment, such as afforestation and check dams, is meant to
- replace the dead storage requirement in the design of the reservoir at the site
- raise the soil salinity in the command area downstream of the dam
- reduce erosion so sediment delivery falls and the reservoir life is extended
- increase the flood peaks so that the reservoir fills faster every monsoon season
Show answer & solution
Answer: (C) reduce erosion so sediment delivery falls and the reservoir life is extended
Lower sediment yield slows the loss of storage.
Question 3
A major cause of waterlogging in canal commands is
- withdrawal of groundwater by tube wells in excess of the recharge in the area
- a shortage of canal water supplied to the area by the system
- seepage from unlined canals and over-irrigation with poor drainage
- deep ploughing that opens up the soil and lets the water drain away quickly
Show answer & solution
Answer: (C) seepage from unlined canals and over-irrigation with poor drainage
Seepage and excess applications raise the water table when drainage is inadequate.
Question 4
Salinisation of irrigated land is commonly caused by
- wind erosion that deposits salt-laden dust onto the cropped fields every year
- deep percolation of fresh canal water below the root zone
- capillary rise of shallow saline groundwater, then evaporation leaving salts
- heavy rainfall that dissolves the salts and brings them up to the surface
Show answer & solution
Answer: (C) capillary rise of shallow saline groundwater, then evaporation leaving salts
Evaporation of capillary water at the surface concentrates dissolved salts.
Question 5
Subsurface drains are installed in waterlogged land to
- carry the surface runoff of the field directly to the river without storage
- raise the water table so that the crop is supplied by capillary rise
- recharge the groundwater by supplying canal water to the root zone
- intercept and remove excess water, lowering the water table below the roots
Show answer & solution
Answer: (D) intercept and remove excess water, lowering the water table below the roots
Subsurface drainage controls the water table at a safe depth.
Question 6
Open surface drains remove excess water effectively only if
- they are graded properly and lead to an adequate outlet
- they are built with zero gradient so that water is held in the drain
- they slope towards the irrigated field instead of away from it
- no outlet is provided, so that the water infiltrates in the drain
Show answer & solution
Answer: (A) they are graded properly and lead to an adequate outlet
Drains need gradient and an outlet that can carry the water away.
Question 7
Leaching of saline soil consists of
- withholding irrigation so that the salts crystallise on the soil surface in the sun
- applying extra water that carries salts below the root zone, with drainage
- adding gypsum to the soil without applying any extra water
- ploughing the salty topsoil down into the root zone of the following crop
Show answer & solution
Answer: (B) applying extra water that carries salts below the root zone, with drainage
Extra water flushes soluble salts, provided drainage removes the leachate.
Question 8
Reclamation of waterlogged and saline land generally needs
- extra irrigation water applied to the land without providing any drainage
- continuous flooding of the land to dilute the salts present
- removal of the crop and leaving the land fallow for several consecutive years
- drainage, leaching and better water management, often with canal lining
Show answer & solution
Answer: (D) drainage, leaching and better water management, often with canal lining
A combined approach is needed; in Pakistan WAPDA's SCARP schemes combined tube-well drainage with canal improvements.
Question 9
Waterlogging and salinity in canal commands show that
- waterlogging and salinity arise only from rainfall, unrelated to irrigation
- irrigation raises productivity on all soils without any side effects
- these problems are limited to the rainfed areas outside the canal commands
- irrigation without matching drainage and water management can degrade land
Show answer & solution
Answer: (D) irrigation without matching drainage and water management can degrade land
Irrigation must be planned together with drainage.
Question 10
Dams are classified on the basis of construction material as
- lined, unlined and composite dams, among others
- aqueducts, siphons and super-passages, among others
- weirs, barrages and diversion headworks, among others
- earth, rockfill, concrete and masonry dams, among others
Show answer & solution
Answer: (D) earth, rockfill, concrete and masonry dams, among others
Examples include Tarbela on the Indus, an earth and rockfill dam, and Mangla on the Jhelum, an earth-fill dam.
Question 11
The phreatic line in an earth dam is the
- boundary between the upstream and downstream slopes of the embankment
- line of the maximum reservoir level drawn on the upstream face
- centre line of the dam crest, running along its full length
- upper boundary of seepage flow, below which the dam body is saturated
Show answer & solution
Answer: (D) upper boundary of seepage flow, below which the dam body is saturated
It marks the top flow line of seepage through the embankment.
Question 12
Slope stability of an earth dam is checked for
- several cases, such as end of construction, steady seepage and rapid drawdown
- only the empty reservoir condition just after the construction is complete
- only the condition of flood water overtopping the dam crest
- only the full reservoir condition, with no seepage assumed through the dam
Show answer & solution
Answer: (A) several cases, such as end of construction, steady seepage and rapid drawdown
Each condition can govern, so all critical cases must be checked.
Question 13
The freeboard of a dam is the
- vertical distance between the maximum water level and the dam crest
- height of the dam above the river bed
- distance between the dead storage level and the minimum drawdown level
- depth of water above the spillway crest at the design flood
Show answer & solution
Answer: (A) vertical distance between the maximum water level and the dam crest
Freeboard guards against overtopping by waves and surges.
Question 14
Dam instrumentation such as piezometers and settlement markers is installed to
- verify the trap efficiency of the reservoir from sediment samples
- detect early signs of seepage, pore pressure or movement
- monitor the crop yields in the command area below the dam
- avoid the need for any foundation investigation before construction
Show answer & solution
Answer: (B) detect early signs of seepage, pore pressure or movement
Monitoring gives early warning so that corrective action can be taken.
Question 15
The type of dam at a site is selected mainly by considering
- the length of the canal system downstream and the type of lining it will have
- foundation geology, local materials, valley topography and dam height and purpose
- the cropping pattern of the command area downstream alone
- the rainfall intensity at the dam site during the monsoon season alone
Show answer & solution
Answer: (B) foundation geology, local materials, valley topography and dam height and purpose
These site factors decide between gravity, earth or rockfill options.
Question 16
A reservoir formed by a dam serves mainly to
- divert the river flow into canals with no storage at all
- raise the flood peaks of the river downstream of the dam
- replace the natural recharge of the groundwater of the area
- store surplus flows for release during low-flow periods
Show answer & solution
Answer: (D) store surplus flows for release during low-flow periods
A reservoir matches fluctuating inflows to the demand.
Question 17
Reservoir operation studies, such as the mass curve method, are used to determine the
- storage needed to meet a demand pattern with acceptable reliability
- rate of silting of the reservoir from the catchment area
- seepage rate through the body of the dam in a wet year
- design flood discharge of the spillway from the rainfall record alone
Show answer & solution
Answer: (A) storage needed to meet a demand pattern with acceptable reliability
Historical inflows are compared with demand to size storage.
Question 18
A filter in the downstream section of an earth dam serves to
- increase the pore pressure in the downstream shell of the earth dam
- provide an impervious core that stops the seepage through the dam completely
- protect the upstream face of the dam from wave action
- let seepage leave while retaining fine particles, preventing piping
Show answer & solution
Answer: (D) let seepage leave while retaining fine particles, preventing piping
Graded filters stop soil particles from being carried away by seepage.
Question 19
Drainage galleries in a concrete gravity dam serve to
- intercept seepage and reduce the uplift pressure
- pass flood discharge in place of a separate spillway
- increase the weight of the dam to improve its stability
- provide storage space for the sediment brought by the river
Show answer & solution
Answer: (A) intercept seepage and reduce the uplift pressure
Relieving seepage pressure improves the stability of the dam.
Question 20
A cutoff (core wall or trench) in an earth dam is provided to
- serve as the spillway of the dam during the passage of floods
- reduce seepage through the dam and foundation and check piping
- increase seepage through the foundation of the dam to relieve the pressure
- raise the phreatic line in the downstream shell of the dam
Show answer & solution
Answer: (B) reduce seepage through the dam and foundation and check piping
It limits seepage flow and the risk of internal erosion.
Question 21
Piping failure in an earth dam is
- failure of a conduit pipe passing through the body of the dam and its outlet
- sliding of the downstream slope under the weight of the saturated soil
- overtopping of the dam crest by flood water released from the spillway
- progressive internal erosion that carries away fine soil and enlarges a channel
Show answer & solution
Answer: (D) progressive internal erosion that carries away fine soil and enlarges a channel
Piping can grow into a catastrophic breach if not controlled.
Question 22
A gravity dam resists the water pressure mainly through
- uplift acting upward on the base
- its own weight and the friction at the base
- tension in steel reinforcement in the body
- arch action transferring load to the abutments
Show answer & solution
Answer: (B) its own weight and the friction at the base
Self-weight and base friction provide stability against sliding and overturning.
Question 23
An earth dam is more suitable than a concrete gravity dam when
- the spillway has to pass the flood over the body of the dam itself
- good earth is plentiful nearby and the foundation is too weak for concrete
- a narrow gorge with sound abutments permits an arch to be built
- a strong rock foundation and abundant good aggregate are available
Show answer & solution
Answer: (B) good earth is plentiful nearby and the foundation is too weak for concrete
Earth dams can be built on weaker foundations using local materials.
Question 24
Unlike many concrete dams, an earth dam
- can be designed to pass floods over its crest like an ogee spillway
- needs a separate spillway only when its height exceeds 100 m
- needs no spillway when the freeboard is 1 m
- must not be overtopped, so a separate spillway must pass the floods
Show answer & solution
Answer: (D) must not be overtopped, so a separate spillway must pass the floods
Overtopping can erode and breach an embankment.
Question 25
A spillway is provided at a dam mainly to
- generate power by passing the normal flows of the river
- flush the sediment from the dead storage of the reservoir regularly
- supply water to the irrigation canals on demand throughout the year
- pass excess flood water safely and protect the dam from overtopping
Show answer & solution
Answer: (D) pass excess flood water safely and protect the dam from overtopping
The spillway handles floods beyond the available storage.
Question 26
The ogee spillway profile follows
- a flat horizontal crest that slows down the flow passing over it
- a stepped surface that dissipates energy on the crest itself
- the lower nappe of a free-falling jet, to avoid negative pressure
- a broad crest with a sharp edge at the upstream end of the crest
Show answer & solution
Answer: (C) the lower nappe of a free-falling jet, to avoid negative pressure
This shape reduces cavitation risk.
Question 27
A chute spillway conveys the discharge
- over the crest and the downstream face of the embankment
- in a separate steep open channel beside the embankment
- through a small pipe in the middle of the dam
- over a siphon through the embankment
Show answer & solution
Answer: (B) in a separate steep open channel beside the embankment
The chute is a lined steep channel beside the embankment, used where the dam body itself cannot be overtopped.
Question 28
Gates on a spillway permit
- omission of the crest profile in the design of the spillway
- permanent storage above the crest level of the spillway
- active regulation of the reservoir level and discharge
- a fixed discharge as with an ungated crest at the same level
Show answer & solution
Answer: (C) active regulation of the reservoir level and discharge
Gates add operating flexibility beyond a fixed crest.
Question 29
A stilling basin at the toe of a spillway is provided to
- raise the tailwater level permanently below the dam to submerge the toe
- dissipate the energy of the fast flow and protect the riverbed and dam toe
- increase the velocity of flow in the river downstream of the dam
- store the sediment brought down by the river from the reservoir
Show answer & solution
Answer: (B) dissipate the energy of the fast flow and protect the riverbed and dam toe
A hydraulic jump in the basin destroys excess energy.
Question 30
Uplift pressure on a concrete gravity dam is the
- wave-induced pressure acting on the dam crest and parapet during storms
- horizontal thrust of the water acting on the upstream face of the dam
- upward water pressure from seepage under the dam, reducing its effective weight
- pressure of silt deposits acting against the dam wall
Show answer & solution
Answer: (C) upward water pressure from seepage under the dam, reducing its effective weight
Uplift reduces resistance to sliding and overturning.
Question 31
Dead storage of a reservoir is the
- total volume of the reservoir at the full supply level of the dam
- volume below the minimum drawdown level, kept for sediment, not for releases
- volume above the full supply level, kept for absorbing the floods
- volume between the minimum and full supply levels, used for the releases
Show answer & solution
Answer: (B) volume below the minimum drawdown level, kept for sediment, not for releases
It accommodates sediment accumulation over the life of the reservoir.
Question 32
Live storage of a reservoir is the
- sum of the dead storage and the surcharge storage of the reservoir at the site
- volume between minimum drawdown and conservation levels, available for releases
- volume below the lowest outlet, reserved for the silt to settle in
- volume between the normal and maximum flood levels of the reservoir
Show answer & solution
Answer: (B) volume between minimum drawdown and conservation levels, available for releases
Live storage is the usable part of the reservoir.
Question 33
Flood (surcharge) storage in a reservoir is the volume
- between the normal conservation level and the maximum flood level, used temporarily
- below the minimum drawdown level of the reservoir at all times of the year
- kept permanently for the sediment brought by the river
- between the minimum drawdown and the full supply level of the reservoir
Show answer & solution
Answer: (A) between the normal conservation level and the maximum flood level, used temporarily
It temporarily absorbs flood inflow and attenuates the peak.
Question 34
Reservoir sedimentation is the
- scouring of the reservoir bed by the flow entering it from the river
- progressive deposition of sediment, which reduces the storage capacity
- gradual gain in the storage capacity from compaction of the bed deposits
- growth of weeds that reduces the water surface of the reservoir
Show answer & solution
Answer: (B) progressive deposition of sediment, which reduces the storage capacity
Deposits fill the basin and reduce useful capacity over time.
Question 35
The trap efficiency of a reservoir is the
- percentage of incoming sediment retained in the reservoir
- percentage of live storage used each year
- percentage of spillway discharge passed with the gates open
- percentage of inflow volume retained in the reservoir
Show answer & solution
Answer: (A) percentage of incoming sediment retained in the reservoir
It measures sediment retention.
Question 36
- salts accumulate in the topsoil because the water table falls below the roots
- the canal supply to the area is cut off for a long period of the year
- the water table rises into the root zone, impairing aeration and crop growth
- soil moisture falls below the wilting point for long periods
Show answer & solution
Answer: (C) the water table rises into the root zone, impairing aeration and crop growth
A high water table drives out air from the root zone.
Question 37
- fall of the soil pH below 4 due to acid rain on the cultivated land
- harmful accumulation of soluble salts in the root zone
- excess of organic matter in the topsoil of the field and the root zone
- deficiency of nitrogen in the root zone of the crop in the field
Show answer & solution
Answer: (B) harmful accumulation of soluble salts in the root zone
Salts impair crop growth and yield.
Question 38
A siphon spillway works by
- a drop-inlet shaft carrying the water down to a tunnel through the abutment
- an open channel carrying the flow over a fixed crest on the embankment
- an airtight conduit that is primed so water discharges by siphonic action
- lifting a gate to release the water from the reservoir
Show answer & solution
Answer: (C) an airtight conduit that is primed so water discharges by siphonic action
Siphonic action gives a discharge behaviour unlike a weir.