Plant Economics & Safety: Cost Estimation

Chemical Engineering · Plant Economics & Safety

41 questions, each with the answer and a worked solution.

Practice interactively and track your score →
Question 1

What is fixed capital investment?

  1. The working capital only
  2. The cost of wages
  3. The money for raw materials
  4. The capital needed for purchasing and installing equipment, buildings and facilities of a plant
Show answer & solution

Answer: (D) The capital needed for purchasing and installing equipment, buildings and facilities of a plant

It includes direct and indirect costs.

Question 2

What is working capital?

  1. The cost of design
  2. Capital tied up in raw materials, product inventory, receivables and cash needed to operate the plant
  3. The cost of land only
  4. The cost of equipment
Show answer & solution

Answer: (B) Capital tied up in raw materials, product inventory, receivables and cash needed to operate the plant

It is recovered at the end of the project.

Question 3

What is the typical working capital as a fraction of total capital investment?

  1. About 1%
  2. About 10–20%
  3. About 50%
  4. About 80%
Show answer & solution

Answer: (B) About 10–20%

It depends on inventory and credit terms.

Question 4

What is total capital investment?

  1. Fixed capital only
  2. Working capital only
  3. Fixed capital investment plus working capital (and start-up costs)
  4. Annual operating cost
Show answer & solution

Answer: (C) Fixed capital investment plus working capital (and start-up costs)

Land is included in fixed capital and not depreciated.

Question 5

What does the six-tenths rule state?

  1. Plant cost varies with capacity raised to about the power 0.6
  2. Cost varies with capacity squared
  3. Cost is proportional to capacity
  4. Cost is independent of capacity
Show answer & solution

Answer: (A) Plant cost varies with capacity raised to about the power 0.6

C₂ = C₁(Q₂/Q₁)^0.6.

Question 6

By what factor does the cost of a plant rise if its capacity is doubled, using the six-tenths rule?

  1. 0.6
  2. 1.2
  3. About 1.52
  4. 2
Show answer & solution

Answer: (C) About 1.52

2^0.6 = 1.516.

Question 7

What is the economy of scale in plant design?

  1. Lower cost per unit of capacity for larger plants
  2. Higher unit cost for larger plants
  3. No relation between size and cost
  4. Equal cost per unit at all sizes
Show answer & solution

Answer: (A) Lower cost per unit of capacity for larger plants

It follows from cost exponents below 1.

Question 8

What is the purpose of cost indices such as the Chemical Engineering Plant Cost Index (CEPCI)?

  1. Calculating taxes
  2. Measuring plant capacity
  3. Measuring profit
  4. Updating past cost data to present values to account for inflation
Show answer & solution

Answer: (D) Updating past cost data to present values to account for inflation

C₂ = C₁ × (I₂/I₁).

Question 9

What is the present cost of equipment that cost Rs 100,000 when the index was 400 if the index is now 800?

  1. Rs 200,000
  2. Rs 400,000
  3. Rs 50,000
  4. Rs 100,000
Show answer & solution

Answer: (A) Rs 200,000

C = 100,000 × 800/400.

Question 10

What is the Lang factor method?

  1. Estimating labour hours
  2. Estimating fixed capital by multiplying delivered equipment cost by a factor for plant type
  3. Estimating raw material cost
  4. Calculating depreciation
Show answer & solution

Answer: (B) Estimating fixed capital by multiplying delivered equipment cost by a factor for plant type

Lang's factor is about 4.7 for fluid processing plants.

Question 11

What is the original Lang factor for a fluid processing plant?

  1. About 1.0
  2. About 2.0
  3. About 4.74
  4. About 10
Show answer & solution

Answer: (C) About 4.74

It is about 3.1 for solids processing plants.

Question 12

What are direct costs in fixed capital?

  1. Engineering and supervision only
  2. Contingency only
  3. Contractor fees only
  4. Purchased equipment, installation, piping, instrumentation, electrical, buildings and site development
Show answer & solution

Answer: (D) Purchased equipment, installation, piping, instrumentation, electrical, buildings and site development

Indirect costs include engineering, construction expenses and contingency.

Question 13

What is a contingency allowance in a cost estimate?

  1. An amount added to cover unforeseen costs and estimating uncertainties
  2. The profit margin
  3. A cost for raw materials
  4. The working capital
Show answer & solution

Answer: (A) An amount added to cover unforeseen costs and estimating uncertainties

It is often 10–20% of fixed capital.

Question 14

What is an order-of-magnitude estimate?

  1. A contractor's bid
  2. A detailed estimate within ±5%
  3. A rough estimate based on similar plants, typically accurate to about ±30–50%
  4. A final cost report
Show answer & solution

Answer: (C) A rough estimate based on similar plants, typically accurate to about ±30–50%

Accuracy improves as design detail increases.

Question 15

What is a definitive (detailed) estimate?

  1. A cost index update
  2. An estimate based on detailed drawings and vendor quotations, accurate to about ±5–10%
  3. A ratio estimate
  4. A rough estimate
Show answer & solution

Answer: (B) An estimate based on detailed drawings and vendor quotations, accurate to about ±5–10%

It is prepared for final authorisation.

Question 16

What is purchased equipment cost usually based on?

  1. The plant's total revenue
  2. Land area only
  3. Employee wages
  4. Vendor quotations, cost charts or correlations using equipment size
Show answer & solution

Answer: (D) Vendor quotations, cost charts or correlations using equipment size

Delivery and installation are added separately.

Question 17

What is the installation cost of process equipment typically as a fraction of purchased cost?

  1. About 1%
  2. Zero
  3. About 300%
  4. About 25–55%
Show answer & solution

Answer: (D) About 25–55%

It depends on equipment type.

Question 18

What is a battery limit plant?

  1. The whole site including utilities
  2. A battery manufacturing plant
  3. The process area itself, excluding offsites and utilities
  4. A storage area only
Show answer & solution

Answer: (C) The process area itself, excluding offsites and utilities

Offsites include tank farms, utilities and buildings.

Question 19

What are offsites in plant cost estimation?

  1. Facilities outside the process units such as utilities, storage, effluent treatment and administration buildings
  2. The process units only
  3. The raw materials
  4. The labour cost
Show answer & solution

Answer: (A) Facilities outside the process units such as utilities, storage, effluent treatment and administration buildings

Offsites may add 20–50% to battery limit cost.

Question 20

What is the cost exponent typically used for individual equipment such as vessels and exchangers?

  1. About 0.1
  2. About 0.5–0.7
  3. About 1.5
  4. About 2
Show answer & solution

Answer: (B) About 0.5–0.7

Each equipment type has its own exponent.

Question 21

What is the cost of a vessel twice as large if the cost exponent is 0.5 and the original cost is Rs 1 million?

  1. Rs 1 million
  2. Rs 2 million
  3. Rs 4 million
  4. About Rs 1.41 million
Show answer & solution

Answer: (D) About Rs 1.41 million

2^0.5 = 1.414.

Question 22

Why is land not depreciated?

  1. Land does not wear out or lose value through use
  2. Land is too cheap
  3. Land is not an asset
  4. Land is always rented
Show answer & solution

Answer: (A) Land does not wear out or lose value through use

It is included in investment but recovered at the end.

Question 23

What is start-up cost?

  1. Taxes
  2. Raw material cost in normal operation
  3. Expenses incurred to bring a new plant into stable operation, such as modifications and initial losses
  4. Depreciation
Show answer & solution

Answer: (C) Expenses incurred to bring a new plant into stable operation, such as modifications and initial losses

It is often about 5–10% of fixed capital.

Question 24

What is the main effect of exchange rate changes on Pakistani plant projects?

  1. It affects only wages
  2. Imported equipment costs in rupees rise when the rupee depreciates
  3. No effect on cost
  4. It lowers all costs
Show answer & solution

Answer: (B) Imported equipment costs in rupees rise when the rupee depreciates

Much process equipment is imported.

Question 25

What is a turnaround (shutdown) cost?

  1. The cost of planned periodic plant shutdown for maintenance and inspection
  2. The cost of raw materials
  3. The cost of utilities only
  4. The cost of new plant
Show answer & solution

Answer: (A) The cost of planned periodic plant shutdown for maintenance and inspection

Turnarounds may occur every 2–5 years.

Question 26

What is the cost of a 200 m² heat exchanger if a 100 m² unit costs Rs 5 million and the cost exponent is 0.6?

  1. Rs 10 million
  2. About Rs 7.6 million
  3. Rs 5 million
  4. About Rs 6.2 million
Show answer & solution

Answer: (B) About Rs 7.6 million

5 × 2^0.6 = 7.58.

Question 27

What is a factorial cost estimate?

  1. An estimate of plant cost obtained by multiplying equipment cost by factors for installation, piping, instruments and other items
  2. An operating cost estimate
  3. A cost index update only
  4. A detailed contractor bid
Show answer & solution

Answer: (A) An estimate of plant cost obtained by multiplying equipment cost by factors for installation, piping, instruments and other items

Hand's method uses separate factors for each equipment type.

Question 28

What is the main source of error in early-stage capital cost estimates?

  1. Exact vendor quotes
  2. Too many drawings
  3. Exchange rate printing errors
  4. Incomplete design definition
Show answer & solution

Answer: (D) Incomplete design definition

Accuracy improves as engineering progresses.

Question 29

What is location factor in cost estimation?

  1. A tax rate
  2. A factor for plant capacity
  3. A depreciation rate
  4. A factor adjusting plant cost for differences in labour, materials and logistics between sites
Show answer & solution

Answer: (D) A factor adjusting plant cost for differences in labour, materials and logistics between sites

Remote sites usually cost more.

Question 30

What does the term CAPEX mean?

  1. Tax expenses
  2. Annual revenue
  3. Capital expenditure on fixed assets
  4. Operating expenditure
Show answer & solution

Answer: (C) Capital expenditure on fixed assets

OPEX means operating expenditure.

Question 31

What is OPEX?

  1. Capital expenditure
  2. Operating expenditure, the ongoing costs of running a plant
  3. Working capital
  4. Land cost
Show answer & solution

Answer: (B) Operating expenditure, the ongoing costs of running a plant

It includes raw materials, utilities, labour and maintenance.

Question 32

What fraction of fixed capital is typically allowed for engineering and supervision?

  1. About 1%
  2. About 10–15% (or about 30% of purchased equipment cost)
  3. About 50%
  4. About 80%
Show answer & solution

Answer: (B) About 10–15% (or about 30% of purchased equipment cost)

It is an indirect cost.

Question 33

What does the term grassroots plant mean in cost estimation?

  1. A completely new plant on an undeveloped site including all offsites
  2. A small pilot plant
  3. A rented plant
  4. An expansion of an existing plant
Show answer & solution

Answer: (A) A completely new plant on an undeveloped site including all offsites

Grassroots costs are higher than battery limit costs.

Question 34

What is the main reason pilot plant data are valuable for cost estimation?

  1. They reduce technical uncertainty in design and therefore contingency
  2. They eliminate scale-up
  3. They replace engineering
  4. They give exact costs
Show answer & solution

Answer: (A) They reduce technical uncertainty in design and therefore contingency

They cost less than design studies.

Question 35

What is a cost escalation clause?

  1. A penalty clause
  2. A clause to reduce cost
  3. A warranty
  4. A contract term adjusting price for inflation in materials and labour over time
Show answer & solution

Answer: (D) A contract term adjusting price for inflation in materials and labour over time

It is common in long projects.

Question 36

What is the typical cost exponent for a complete process plant?

  1. About 0.1
  2. About 0.6–0.7
  3. About 1.5
  4. About 2
Show answer & solution

Answer: (B) About 0.6–0.7

Individual items vary widely.

Question 37

What does a cost index of 1.2 times the base year imply for a cost estimate?

  1. Costs doubled
  2. Costs have fallen by 20%
  3. Costs have risen by 20% since the base year
  4. No change
Show answer & solution

Answer: (C) Costs have risen by 20% since the base year

Indices track inflation of plant costs.

Question 38

What is the main purpose of a feasibility study?

  1. Building the plant
  2. Training staff
  3. Assessing technical and economic viability of a proposed project before investment
  4. Selling products
Show answer & solution

Answer: (C) Assessing technical and economic viability of a proposed project before investment

It includes market, cost and profitability analysis.

Question 39

What is a market study in project evaluation?

  1. A study of equipment
  2. A safety study
  3. A study of plant layout
  4. An analysis of demand, supply, prices and competition for the product
Show answer & solution

Answer: (D) An analysis of demand, supply, prices and competition for the product

Plant capacity is chosen from it.

Question 40

What is the main purpose of a cost estimate classification such as AACE classes 1 to 5?

  1. Defining expected accuracy ranges based on project definition level
  2. Rating employees
  3. Rating safety
  4. Rating quality
Show answer & solution

Answer: (A) Defining expected accuracy ranges based on project definition level

Class 5 is the roughest estimate.

Question 41

What is the delivered equipment cost?

  1. Purchase cost only
  2. Purchased cost plus freight, insurance and duties to bring equipment to site
  3. Installation cost only
  4. Engineering cost
Show answer & solution

Answer: (B) Purchased cost plus freight, insurance and duties to bring equipment to site

Freight may add 5–10% for imported items.