What is fixed capital investment?
Show answer & solution
Answer: (D) The capital needed for purchasing and installing equipment, buildings and facilities of a plant
It includes direct and indirect costs.
Chemical Engineering · Plant Economics & Safety
41 questions, each with the answer and a worked solution.
Practice interactively and track your score →What is fixed capital investment?
Answer: (D) The capital needed for purchasing and installing equipment, buildings and facilities of a plant
It includes direct and indirect costs.
What is working capital?
Answer: (B) Capital tied up in raw materials, product inventory, receivables and cash needed to operate the plant
It is recovered at the end of the project.
What is the typical working capital as a fraction of total capital investment?
Answer: (B) About 10–20%
It depends on inventory and credit terms.
What is total capital investment?
Answer: (C) Fixed capital investment plus working capital (and start-up costs)
Land is included in fixed capital and not depreciated.
What does the six-tenths rule state?
Answer: (A) Plant cost varies with capacity raised to about the power 0.6
C₂ = C₁(Q₂/Q₁)^0.6.
By what factor does the cost of a plant rise if its capacity is doubled, using the six-tenths rule?
Answer: (C) About 1.52
2^0.6 = 1.516.
What is the economy of scale in plant design?
Answer: (A) Lower cost per unit of capacity for larger plants
It follows from cost exponents below 1.
What is the purpose of cost indices such as the Chemical Engineering Plant Cost Index (CEPCI)?
Answer: (D) Updating past cost data to present values to account for inflation
C₂ = C₁ × (I₂/I₁).
What is the present cost of equipment that cost Rs 100,000 when the index was 400 if the index is now 800?
Answer: (A) Rs 200,000
C = 100,000 × 800/400.
What is the Lang factor method?
Answer: (B) Estimating fixed capital by multiplying delivered equipment cost by a factor for plant type
Lang's factor is about 4.7 for fluid processing plants.
What is the original Lang factor for a fluid processing plant?
Answer: (C) About 4.74
It is about 3.1 for solids processing plants.
What are direct costs in fixed capital?
Answer: (D) Purchased equipment, installation, piping, instrumentation, electrical, buildings and site development
Indirect costs include engineering, construction expenses and contingency.
What is a contingency allowance in a cost estimate?
Answer: (A) An amount added to cover unforeseen costs and estimating uncertainties
It is often 10–20% of fixed capital.
What is an order-of-magnitude estimate?
Answer: (C) A rough estimate based on similar plants, typically accurate to about ±30–50%
Accuracy improves as design detail increases.
What is a definitive (detailed) estimate?
Answer: (B) An estimate based on detailed drawings and vendor quotations, accurate to about ±5–10%
It is prepared for final authorisation.
What is purchased equipment cost usually based on?
Answer: (D) Vendor quotations, cost charts or correlations using equipment size
Delivery and installation are added separately.
What is the installation cost of process equipment typically as a fraction of purchased cost?
Answer: (D) About 25–55%
It depends on equipment type.
What is a battery limit plant?
Answer: (C) The process area itself, excluding offsites and utilities
Offsites include tank farms, utilities and buildings.
What are offsites in plant cost estimation?
Answer: (A) Facilities outside the process units such as utilities, storage, effluent treatment and administration buildings
Offsites may add 20–50% to battery limit cost.
What is the cost exponent typically used for individual equipment such as vessels and exchangers?
Answer: (B) About 0.5–0.7
Each equipment type has its own exponent.
What is the cost of a vessel twice as large if the cost exponent is 0.5 and the original cost is Rs 1 million?
Answer: (D) About Rs 1.41 million
2^0.5 = 1.414.
Why is land not depreciated?
Answer: (A) Land does not wear out or lose value through use
It is included in investment but recovered at the end.
What is start-up cost?
Answer: (C) Expenses incurred to bring a new plant into stable operation, such as modifications and initial losses
It is often about 5–10% of fixed capital.
What is the main effect of exchange rate changes on Pakistani plant projects?
Answer: (B) Imported equipment costs in rupees rise when the rupee depreciates
Much process equipment is imported.
What is a turnaround (shutdown) cost?
Answer: (A) The cost of planned periodic plant shutdown for maintenance and inspection
Turnarounds may occur every 2–5 years.
What is the cost of a 200 m² heat exchanger if a 100 m² unit costs Rs 5 million and the cost exponent is 0.6?
Answer: (B) About Rs 7.6 million
5 × 2^0.6 = 7.58.
What is a factorial cost estimate?
Answer: (A) An estimate of plant cost obtained by multiplying equipment cost by factors for installation, piping, instruments and other items
Hand's method uses separate factors for each equipment type.
What is the main source of error in early-stage capital cost estimates?
Answer: (D) Incomplete design definition
Accuracy improves as engineering progresses.
What is location factor in cost estimation?
Answer: (D) A factor adjusting plant cost for differences in labour, materials and logistics between sites
Remote sites usually cost more.
What does the term CAPEX mean?
Answer: (C) Capital expenditure on fixed assets
OPEX means operating expenditure.
What is OPEX?
Answer: (B) Operating expenditure, the ongoing costs of running a plant
It includes raw materials, utilities, labour and maintenance.
What fraction of fixed capital is typically allowed for engineering and supervision?
Answer: (B) About 10–15% (or about 30% of purchased equipment cost)
It is an indirect cost.
What does the term grassroots plant mean in cost estimation?
Answer: (A) A completely new plant on an undeveloped site including all offsites
Grassroots costs are higher than battery limit costs.
What is the main reason pilot plant data are valuable for cost estimation?
Answer: (A) They reduce technical uncertainty in design and therefore contingency
They cost less than design studies.
What is a cost escalation clause?
Answer: (D) A contract term adjusting price for inflation in materials and labour over time
It is common in long projects.
What is the typical cost exponent for a complete process plant?
Answer: (B) About 0.6–0.7
Individual items vary widely.
What does a cost index of 1.2 times the base year imply for a cost estimate?
Answer: (C) Costs have risen by 20% since the base year
Indices track inflation of plant costs.
What is the main purpose of a feasibility study?
Answer: (C) Assessing technical and economic viability of a proposed project before investment
It includes market, cost and profitability analysis.
What is a market study in project evaluation?
Answer: (D) An analysis of demand, supply, prices and competition for the product
Plant capacity is chosen from it.
What is the main purpose of a cost estimate classification such as AACE classes 1 to 5?
Answer: (A) Defining expected accuracy ranges based on project definition level
Class 5 is the roughest estimate.
What is the delivered equipment cost?
Answer: (B) Purchased cost plus freight, insurance and duties to bring equipment to site
Freight may add 5–10% for imported items.