Question 1

What is a quantitative plan of action prepared for a future period called?

  1. Variance
  2. Forecast only
  3. Budget
  4. Standard
Show answer & solution

Answer: (C) Budget

Budgets are used for planning, coordination and control.

Question 2

What is the factor that limits the activities of an organization and is considered first when preparing budgets called?

  1. Margin of safety
  2. Contribution
  3. Cost driver
  4. Principal budget factor
Show answer & solution

Answer: (D) Principal budget factor

Sales demand is often the principal budget factor.

Question 3

Which budget is usually prepared first because it is the main limiting factor in most organizations?

  1. Capital budget
  2. Master budget
  3. Sales budget
  4. Cash budget
Show answer & solution

Answer: (C) Sales budget

Production and purchases budgets depend on the sales budget.

Question 4

How is the number of units to be produced in a production budget calculated?

  1. Sales × price
  2. Budgeted sales + closing finished goods inventory − opening finished goods inventory
  3. Sales − closing inventory
  4. Opening inventory + sales
Show answer & solution

Answer: (B) Budgeted sales + closing finished goods inventory − opening finished goods inventory

Inventory changes adjust production to sales.

Question 5

Budgeted sales are 10,000 units, desired closing inventory is 2,000 units and opening inventory is 1,500 units. How many units should be produced?

  1. 9,500 units
  2. 13,500 units
  3. 12,000 units
  4. 10,500 units
Show answer & solution

Answer: (D) 10,500 units

10,000 + 2,000 − 1,500 = 10,500.

Question 6

Which budget shows expected cash receipts and payments for a period?

  1. Capital expenditure budget
  2. Cash budget
  3. Sales budget
  4. Production budget
Show answer & solution

Answer: (B) Cash budget

It shows when borrowing may be needed.

Question 7

What is the summary budget consisting of the budgeted income statement, balance sheet and cash budget called?

  1. Rolling budget
  2. Functional budget
  3. Master budget
  4. Flexible budget
Show answer & solution

Answer: (C) Master budget

It brings together all functional budgets.

Question 8

What is a budget designed to change with the level of activity called?

  1. Incremental budget
  2. Master budget
  3. Fixed budget
  4. Flexible budget
Show answer & solution

Answer: (D) Flexible budget

It is used to compare actual results with the budget for the actual level of activity.

Question 9

What is a budget prepared for one level of activity that does not change with actual output called?

  1. Zero-based budget
  2. Flexible budget
  3. Fixed (static) budget
  4. Rolling budget
Show answer & solution

Answer: (C) Fixed (static) budget

Comparing a fixed budget with actual results at a different activity level can mislead.

Question 10

What is a budget continuously updated by adding a new period as the earliest period ends called?

  1. Rolling (continuous) budget
  2. Zero-based budget
  3. Fixed budget
  4. Master budget
Show answer & solution

Answer: (A) Rolling (continuous) budget

It keeps budgets realistic in changing conditions.

Question 11

What is the approach where managers participate in setting their own budgets called?

  1. Participative (bottom-up) budgeting
  2. Activity-based budgeting
  3. Imposed (top-down) budgeting
  4. Incremental budgeting
Show answer & solution

Answer: (A) Participative (bottom-up) budgeting

It improves motivation but may lead to budget slack.

Question 12

What is the deliberate overestimation of costs or underestimation of revenue in a budget called?

  1. Margin of safety
  2. Contingency
  3. Budgetary slack
  4. Variance
Show answer & solution

Answer: (C) Budgetary slack

It makes budgets easier to achieve.

Question 13

What is the system of assigning responsibility for costs, revenues or investments to individual managers called?

  1. Standard costing
  2. Process costing
  3. Marginal costing
  4. Responsibility accounting
Show answer & solution

Answer: (D) Responsibility accounting

Managers are judged on items they control.

Question 14

Which responsibility centre is accountable only for costs?

  1. Revenue centre
  2. Investment centre
  3. Profit centre
  4. Cost centre
Show answer & solution

Answer: (D) Cost centre

A production department is usually a cost centre.

Question 15

Which responsibility centre is accountable for both revenues and costs?

  1. Profit centre
  2. Expense centre
  3. Cost centre
  4. Revenue centre
Show answer & solution

Answer: (A) Profit centre

A branch or product division is often a profit centre.

Question 16

Which responsibility centre is accountable for revenues, costs and the capital invested?

  1. Cost centre
  2. Revenue centre
  3. Profit centre
  4. Investment centre
Show answer & solution

Answer: (D) Investment centre

Its performance is measured by ROI or residual income.

Question 17

How is return on investment (ROI) for a division calculated?

  1. Divisional profit ÷ capital employed × 100
  2. Capital employed ÷ profit
  3. Sales ÷ profit
  4. Profit − interest
Show answer & solution

Answer: (A) Divisional profit ÷ capital employed × 100

A high ROI shows efficient use of capital.

Question 18

A division earns Rs. 50,000 on investment of Rs. 400,000, and the cost of capital is 10%. What is its residual income?

  1. Rs. 50,000
  2. Rs. 10,000
  3. Rs. 90,000
  4. Rs. 40,000
Show answer & solution

Answer: (B) Rs. 10,000

50,000 − (400,000 × 10%) = 10,000.

Question 19

Why is residual income sometimes preferred to ROI for evaluating divisions?

  1. It ignores capital
  2. It encourages managers to accept projects earning more than the cost of capital
  3. It cannot be calculated
  4. It is always a percentage
Show answer & solution

Answer: (B) It encourages managers to accept projects earning more than the cost of capital

ROI may lead managers to reject projects that lower their divisional ROI.

Question 20

What is the price charged by one division of a company to another division for goods or services called?

  1. Transfer price
  2. Cost price
  3. Sales price
  4. Market price only
Show answer & solution

Answer: (A) Transfer price

It affects the reported profit of both divisions.

Question 21

Which framework measures performance from financial, customer, internal business process and learning and growth perspectives?

  1. DuPont analysis
  2. Balanced scorecard
  3. Porter's five forces
  4. SWOT analysis
Show answer & solution

Answer: (B) Balanced scorecard

It was developed by Kaplan and Norton.

Question 22

What are measures such as customer satisfaction and quality that are not expressed in money called?

  1. Variances
  2. Budgets
  3. Financial ratios
  4. Non-financial performance measures
Show answer & solution

Answer: (D) Non-financial performance measures

They complement financial measures.

Question 23

What is the system of comparing actual results with budgets and taking corrective action called?

  1. Inventory control
  2. Quality control
  3. Budgetary control
  4. Production planning
Show answer & solution

Answer: (C) Budgetary control

It is a key management control tool.

Question 24

Which costs incurred for preventing, appraising and correcting defects are analysed in quality management?

  1. Cost of quality (prevention, appraisal, internal and external failure costs)
  2. Sunk costs
  3. Notional costs
  4. Opportunity costs
Show answer & solution

Answer: (A) Cost of quality (prevention, appraisal, internal and external failure costs)

Total Quality Management aims to reduce failure costs.

Question 25

What is the comparison of an organization's processes and performance with best practices of others called?

  1. Benchmarking
  2. Costing
  3. Budgeting
  4. Forecasting
Show answer & solution

Answer: (A) Benchmarking

It identifies areas for improvement.

Question 26

What is the term for a budget in which each activity must be justified as if it were new each year?

  1. Incremental budget
  2. Rolling budget
  3. Zero-based budget
  4. Flexible budget
Show answer & solution

Answer: (C) Zero-based budget

It helps eliminate wasteful spending.

Question 27

What is the type of budget that allocates resources based on activities and their cost drivers?

  1. Activity-based budgeting
  2. Cash budgeting
  3. Incremental budgeting
  4. Fixed budgeting
Show answer & solution

Answer: (A) Activity-based budgeting

It applies ABC principles to budgeting.

Question 28

Which committee coordinates the preparation and approval of budgets in an organization?

  1. Remuneration committee
  2. Shariah board
  3. Audit committee
  4. Budget committee
Show answer & solution

Answer: (D) Budget committee

The budget officer usually acts as its secretary.

Question 29

What is the document containing instructions, procedures and timetables for budget preparation called?

  1. Prospectus
  2. Cost sheet
  3. Budget report
  4. Budget manual
Show answer & solution

Answer: (D) Budget manual

It ensures consistency in budget preparation.

Question 30

Why is depreciation excluded from a cash budget?

  1. It is a non-cash expense
  2. It is included in sales
  3. It is always paid in advance
  4. It is a capital receipt
Show answer & solution

Answer: (A) It is a non-cash expense

Only actual cash receipts and payments appear.

Question 31

Which budget lists planned purchases of fixed assets such as machinery and buildings?

  1. Labour budget
  2. Capital expenditure budget
  3. Sales budget
  4. Cash budget
Show answer & solution

Answer: (B) Capital expenditure budget

Capital budgets are prepared for several years.

Question 32

What is the period covered by a budget called?

  1. Budget period
  2. Lead time
  3. Payback period
  4. Accounting cycle only
Show answer & solution

Answer: (A) Budget period

Most operating budgets cover one year divided into months or quarters.

Practice these 32 questions interactively →