Where is job costing most suitable?
Show answer & solution
Answer: (D) Where work is done to individual customer specifications, such as repairs or printing orders
Each job is a separate cost unit.
Accounting · Cost Accounting
40 questions, each with the answer and a worked solution.
Practice interactively and track your score →Where is job costing most suitable?
Answer: (D) Where work is done to individual customer specifications, such as repairs or printing orders
Each job is a separate cost unit.
Where is batch costing used?
Answer: (C) Where a group of identical units is produced together, such as medicines or garments
Cost per unit is batch cost ÷ units.
Where is contract costing used?
Answer: (B) For large, long-duration jobs such as building roads, bridges or dams
Each contract has its own account.
Where is process costing used?
Answer: (D) In continuous mass production of similar units, such as cement, sugar or fertilizer
Costs are averaged over output.
What is a job cost sheet?
Answer: (C) A record collecting materials, labour and overheads charged to a particular job
It shows total job cost.
What is the total cost of a job with direct materials Rs 40,000, 200 labour hours at Rs 150 and overheads absorbed at Rs 100 per labour hour?
Answer: (B) Rs 90,000
40,000 + 30,000 + 20,000.
What is the selling price of a job costing Rs 90,000 if profit is 20% of selling price?
Answer: (A) Rs 112,500
90,000 ÷ 0.80.
What are equivalent units in process costing?
Answer: (C) Partly finished units expressed as an equal number of fully finished units
They allow costs to be shared fairly.
What are the equivalent units for conversion if 8,000 units are completed and 2,000 closing units are 60% complete, with no opening work in process?
Answer: (C) 9,200
8,000 + 2,000 × 60%.
What are the equivalent units for materials if materials are added at the start and 8,000 units are completed with 2,000 units in closing work in process?
Answer: (D) 10,000
Closing units are 100% complete for materials.
What are the FIFO equivalent units for conversion if opening WIP is 2,000 units 40% complete, 9,000 units are completed and closing WIP is 3,000 units 50% complete?
Answer: (B) 9,700
1,200 + 7,000 + 1,500.
What are the weighted average equivalent units for conversion if 9,000 units are completed and closing WIP is 3,000 units 50% complete?
Answer: (C) 10,500
9,000 + 1,500.
What is the main difference between the FIFO and weighted average methods in process costing?
Answer: (A) Weighted average combines opening WIP costs with current costs, while FIFO keeps them separate
FIFO shows current-period performance more clearly.
What is normal loss in process costing?
Answer: (B) An expected, unavoidable loss whose cost is absorbed by good output
Its scrap value reduces process cost.
How is abnormal loss valued in process costing?
Answer: (D) At the same cost per unit as good output, then written off to costing profit and loss
This keeps inefficiency out of product cost.
What is an abnormal gain?
Answer: (A) The amount by which actual loss is less than normal loss
It is credited to costing profit and loss.
What is the cost per unit if input is 10,000 kg costing Rs 191,000, normal loss is 5% with scrap value Rs 2 per kg?
Answer: (D) Rs 20
(191,000 − 1,000) ÷ 9,500 expected units.
What is the abnormal loss if input is 10,000 kg, normal loss is 5% and actual output is 9,300 kg?
Answer: (A) 200 kg
Expected output 9,500 − actual 9,300.
What is normal spoilage according to Horngren's cost accounting?
Answer: (B) Spoilage inherent in a production process even under efficient operating conditions
Its cost is part of the cost of good units.
How is the cost of abnormal spoilage treated?
Answer: (A) Recognised as a loss in the period it is detected
It is not expected under efficient operations.
What is rework?
Answer: (C) Units that do not meet standards but are reworked and sold as good finished goods
Rework costs may be normal or abnormal.
Why does the inspection point matter in spoilage accounting?
Answer: (B) Normal spoilage cost is assigned to units that have passed the inspection point
Units not yet inspected bear no spoilage cost.
How are transferred-in costs treated in a subsequent process?
Answer: (D) Like materials added at the start of that process
They are 100% complete for the next process.
What is the cost of 8,000 completed units if cost per equivalent unit is Rs 30 for materials and Rs 20 for conversion?
Answer: (B) Rs 400,000
8,000 × (30 + 20).
What is the value of 2,000 closing units 100% complete for materials (Rs 30 per unit) and 60% complete for conversion (Rs 20 per unit)?
Answer: (A) Rs 84,000
2,000 × 30 + 1,200 × 20.
What is economic batch quantity?
Answer: (C) The batch size that minimises the total of set-up costs and inventory holding costs
It is similar in idea to EOQ.
What is a cost-plus contract?
Answer: (D) A contract where the price is the actual cost plus an agreed profit
Common in government contracts.
What is retention money in contract costing?
Answer: (C) A part of the certified amount withheld by the client until the work proves satisfactory
It is released after the maintenance period.
What is an escalation clause in a contract?
Answer: (B) A clause allowing the price to rise if specified costs increase
It protects the contractor from inflation.
What is service (operating) costing?
Answer: (A) Costing applied to services such as transport, hospitals and power generation
Composite cost units are often used.
What is the cost per passenger-kilometre if total transport cost is Rs 450,000 for 150,000 passenger-kilometres?
Answer: (D) Rs 3
450,000 ÷ 150,000.
Which is a composite cost unit?
Answer: (D) Tonne-kilometre
It combines two measures.
Which cost unit is commonly used in hospitals?
Answer: (C) Patient-day
It measures one patient for one day.
Which cost unit is used in electricity generation?
Answer: (B) Kilowatt-hour
WAPDA and power companies measure output this way.
How is spoilage attributable to a specific job's demanding specifications treated in job costing?
Answer: (A) It is charged to that specific job
Spoilage common to all jobs goes to overhead.
What is operation costing?
Answer: (A) Costing each operation or stage in a continuous production process
It is a refined form of process costing.
What is unit (output) costing?
Answer: (B) Costing used where a single homogeneous product is made, such as bricks
Cost per unit is total cost ÷ output.
What is uniform costing?
Answer: (C) Using the same costing principles by different firms in the same industry
It allows inter-firm comparison.
What does "work certified" mean in contract costing?
Answer: (D) The value of work completed and approved by the client's engineer or architect
Progress payments are based on it.
What happens to the output of one process in multi-process manufacturing?
Answer: (B) It becomes the input of the next process
Costs accumulate through processes.