What is a standard cost?
Show answer & solution
Answer: (A) A predetermined cost per unit under specified working conditions
It is used as a benchmark for control.
Accounting · Management Accounting
40 questions, each with the answer and a worked solution.
Practice interactively and track your score →What is a standard cost?
Answer: (A) A predetermined cost per unit under specified working conditions
It is used as a benchmark for control.
What is an ideal standard?
Answer: (C) A standard achievable only under perfect conditions with no waste or idle time
It may demotivate staff.
What is an attainable standard?
Answer: (B) A standard achievable with efficient operation that allows for normal losses
It is widely seen as most motivating.
What is a basic standard?
Answer: (A) A long-term standard left unchanged to show trends over time
It is rarely used for control.
What is the material price variance if 5,000 kg are bought at Rs 52 per kg and the standard price is Rs 50 per kg?
Answer: (D) Rs 10,000 adverse
(50 − 52) × 5,000.
What is the material usage variance if 1,000 units need a standard 5.2 kg each, 5,000 kg are used and the standard price is Rs 50 per kg?
Answer: (B) Rs 10,000 favourable
(5,200 − 5,000) × 50.
What is the total material cost variance if standard cost of actual output is Rs 260,000 and actual material cost is 5,000 kg at Rs 52?
Answer: (A) Nil
The price and usage variances offset each other.
What is the labour rate variance if 2,000 hours are paid Rs 420,000 and the standard rate is Rs 200 per hour?
Answer: (D) Rs 20,000 adverse
2,000 × 200 − 420,000.
What is the labour efficiency variance if standard hours for actual output are 2,200, actual hours worked are 2,000 and the standard rate is Rs 200?
Answer: (C) Rs 40,000 favourable
(2,200 − 2,000) × 200.
What is the idle time variance if 2,100 hours are paid, 2,000 hours are worked and the standard rate is Rs 200?
Answer: (D) Rs 20,000 adverse
100 idle hours × 200.
What is the variable overhead expenditure variance if actual variable overhead is Rs 130,000 for 2,000 hours and the standard rate is Rs 60 per hour?
Answer: (A) Rs 10,000 adverse
120,000 − 130,000.
What is the variable overhead efficiency variance if standard hours are 2,200, actual hours 2,000 and the standard rate is Rs 60 per hour?
Answer: (C) Rs 12,000 favourable
(2,200 − 2,000) × 60.
What is the fixed overhead expenditure variance if budgeted fixed overhead is Rs 500,000 and actual is Rs 520,000?
Answer: (B) Rs 20,000 adverse
Budget − actual.
What is the fixed overhead volume variance if budgeted output is 10,000 units, actual output 9,000 units and the absorption rate Rs 50 per unit?
Answer: (A) Rs 50,000 adverse
1,000 units short × 50.
What is the sales price variance if 9,000 units are sold at Rs 210 against a standard price of Rs 200?
Answer: (C) Rs 90,000 favourable
(210 − 200) × 9,000.
What is the sales volume contribution variance if budgeted sales are 10,000 units, actual 9,000 units and standard contribution Rs 80 per unit?
Answer: (D) Rs 80,000 adverse
1,000 units × 80.
Which cause could explain a favourable material price variance alongside an adverse usage variance?
Answer: (B) Buying cheaper, lower-quality material that caused more wastage
Variances may be interdependent.
Which cause could explain an adverse labour rate variance?
Answer: (B) A wage increase above standard or use of higher-grade workers
The personnel or production manager may be responsible.
What is a material mix variance?
Answer: (C) A variance arising when the proportions of materials used differ from the standard mix
It applies when materials can be substituted.
What is a yield variance?
Answer: (A) A variance arising when actual output differs from the standard output expected from the input
It often arises in process industries.
What is the difference between planning and operational variances?
Answer: (D) Planning variances arise from unrealistic standards, while operational variances reflect actual performance against a revised standard
Splitting them gives fairer performance assessment.
Which factor should be considered before investigating a variance?
Answer: (A) Its size, controllability, trend and the cost of investigation against the benefit
Not every variance merits investigation.
What is a standard hour?
Answer: (C) The amount of work achievable in one hour at standard efficiency
It measures output in time terms.
What is the efficiency ratio if standard hours for actual output are 2,200 and actual hours worked are 2,000?
Answer: (D) 110%
2,200 ÷ 2,000 × 100.
What is the capacity ratio if actual hours worked are 2,000 and budgeted hours are 2,500?
Answer: (A) 80%
2,000 ÷ 2,500 × 100.
What is the production volume ratio if standard hours of actual output are 2,200 and budgeted hours are 2,500?
Answer: (B) 88%
It equals efficiency ratio × capacity ratio.
What is an operating statement in standard costing?
Answer: (D) A statement reconciling budgeted profit to actual profit through variances
It summarises performance for management.
Why is traditional standard costing seen as less useful in some modern environments?
Answer: (B) Continuous improvement, short product lives and customisation make fixed standards less relevant
Many firms still use it alongside newer methods.
What is kaizen costing?
Answer: (C) Achieving continuous small cost reductions during the production stage
It originated in Japanese manufacturing.
How is target cost calculated?
Answer: (D) Target selling price minus target profit
It is set before the product is designed.
What is the target cost if the target price is Rs 5,000 and the required profit margin is 20% of price?
Answer: (C) Rs 4,000
5,000 − 1,000.
What is the cost gap if the estimated cost is Rs 4,300 and the target cost is Rs 4,000?
Answer: (B) Rs 300
The gap must be closed through design or process changes.
What is life-cycle costing?
Answer: (A) Tracking and accumulating a product's costs and revenues over its whole life
Many costs are committed at the design stage.
How is the fixed overhead volume variance divided further?
Answer: (D) Into capacity and efficiency variances
Capacity relates to hours worked; efficiency to productivity.
What is the advantage of calculating the material price variance at the time of purchase?
Answer: (C) Variances are reported promptly and inventory can be held at standard price
Responsibility lies with the purchasing manager.
What is a standard cost card?
Answer: (A) A record of the standard quantities and prices of each cost element for one unit
It is the basis for variance calculations.
Who is usually responsible for the labour efficiency variance?
Answer: (B) The production manager
It reflects productivity on the shop floor.
Who is usually responsible for the material price variance?
Answer: (A) The purchasing manager
Prices depend on buying decisions.
What does a favourable labour efficiency variance usually indicate?
Answer: (A) Workers took fewer hours than standard for the output achieved
Better training or materials may be the cause.
What is the sales mix variance?
Answer: (A) A variance arising when the actual proportions of products sold differ from the budgeted mix
A shift towards lower-margin products is adverse.