Question 1

What is a budget?

  1. A quantitative plan of action for a future period
  2. An audit report
  3. A tax return
  4. A record of past transactions
Show answer & solution

Answer: (A) A quantitative plan of action for a future period

It is usually expressed in money.

Question 2

What is the principal budget factor?

  1. The interest rate
  2. The largest expense
  3. The factor that limits the organisation's activity, often sales demand
  4. The tax rate
Show answer & solution

Answer: (C) The factor that limits the organisation's activity, often sales demand

It is budgeted first.

Question 3

What is the master budget?

  1. The sales budget only
  2. The audit plan
  3. The production budget only
  4. The summary budget comprising the budgeted income statement, statement of financial position and cash budget
Show answer & solution

Answer: (D) The summary budget comprising the budgeted income statement, statement of financial position and cash budget

It brings all functional budgets together.

Question 4

What is a functional budget?

  1. The master budget
  2. A budget for one function, such as sales, production or purchasing
  3. A cash budget only
  4. A capital budget only
Show answer & solution

Answer: (B) A budget for one function, such as sales, production or purchasing

Functional budgets feed into the master budget.

Question 5

What is the production budget if sales are 10,000 units, opening inventory 1,500 units and closing inventory 2,000 units?

  1. 9,500 units
  2. 10,000 units
  3. 10,500 units
  4. 11,500 units
Show answer & solution

Answer: (C) 10,500 units

10,000 + 2,000 − 1,500.

Question 6

What is the material purchases budget if usage is 21,000 kg, opening stock 4,000 kg and closing stock 3,000 kg?

  1. 20,000 kg
  2. 21,000 kg
  3. 22,000 kg
  4. 28,000 kg
Show answer & solution

Answer: (A) 20,000 kg

21,000 + 3,000 − 4,000.

Question 7

What is the main purpose of a cash budget?

  1. Calculating profit
  2. Calculating depreciation
  3. Valuing inventory
  4. Forecasting cash receipts and payments to identify surpluses and shortages in advance
Show answer & solution

Answer: (D) Forecasting cash receipts and payments to identify surpluses and shortages in advance

It helps arrange finance on time.

Question 8

Which item is excluded from a cash budget?

  1. Loan repayments
  2. Depreciation
  3. Receipts from customers
  4. Wages paid
Show answer & solution

Answer: (B) Depreciation

Depreciation is not a cash flow.

Question 9

What are April cash receipts if 40% of sales are collected in the month of sale and 60% the next month, with March sales Rs 500,000 and April sales Rs 600,000?

  1. Rs 500,000
  2. Rs 540,000
  3. Rs 560,000
  4. Rs 600,000
Show answer & solution

Answer: (B) Rs 540,000

240,000 + 300,000.

Question 10

What is a fixed budget?

  1. A budget that never changes for a decade
  2. A budget for fixed costs only
  3. A budget prepared for one level of activity and not adjusted for actual activity
  4. A flexible budget
Show answer & solution

Answer: (C) A budget prepared for one level of activity and not adjusted for actual activity

It is useful for planning but weak for control.

Question 11

What is a flexible budget?

  1. A budget adjusted to reflect the actual level of activity achieved
  2. A capital budget
  3. A cash budget
  4. A budget for one activity level
Show answer & solution

Answer: (A) A budget adjusted to reflect the actual level of activity achieved

It enables meaningful cost comparisons.

Question 12

What is the flexed budget cost if variable cost is Rs 30 per unit, fixed cost Rs 200,000 and actual output 12,000 units?

  1. Rs 360,000
  2. Rs 600,000
  3. Rs 500,000
  4. Rs 560,000
Show answer & solution

Answer: (D) Rs 560,000

12,000 × 30 + 200,000.

Question 13

What is zero-based budgeting?

  1. Budgeting without targets
  2. Budgeting where every activity must be justified from zero each period
  3. Adding a percentage to last year's budget
  4. Budgeting only for zero-cost items
Show answer & solution

Answer: (B) Budgeting where every activity must be justified from zero each period

It challenges existing spending.

Question 14

What is incremental budgeting?

  1. Starting each budget from zero
  2. Budgeting by activity
  3. Preparing a budget by adjusting the previous period's budget for expected changes
  4. Budgeting only for new items
Show answer & solution

Answer: (C) Preparing a budget by adjusting the previous period's budget for expected changes

It is quick but may carry forward waste.

Question 15

What is the main weakness of incremental budgeting?

  1. It can carry forward past inefficiencies and budgetary slack
  2. It is too detailed
  3. It ignores past data
  4. It takes too long
Show answer & solution

Answer: (A) It can carry forward past inefficiencies and budgetary slack

Zero-based budgeting addresses this.

Question 16

What is a rolling (continuous) budget?

  1. A fixed budget
  2. A budget for one month only
  3. A budget prepared once in five years
  4. A budget kept up to date by adding a new period as each period ends
Show answer & solution

Answer: (D) A budget kept up to date by adding a new period as each period ends

It keeps planning current.

Question 17

What is activity-based budgeting?

  1. Budgeting by sales only
  2. Budgeting by last year's figures
  3. Budgeting by department only
  4. Budgeting based on activities and their cost drivers
Show answer & solution

Answer: (D) Budgeting based on activities and their cost drivers

It links resources to planned activity levels.

Question 18

What is budgetary slack?

  1. An unused budget line
  2. A budget surplus of cash
  3. Deliberate overstatement of costs or understatement of revenues in a budget
  4. A budget variance
Show answer & solution

Answer: (C) Deliberate overstatement of costs or understatement of revenues in a budget

It makes targets easier to achieve.

Question 19

What is participative (bottom-up) budgeting?

  1. Budgeting in which managers responsible for budgets help prepare them
  2. Budgets prepared by the government
  3. Budgets imposed by top management
  4. Budgets prepared by auditors
Show answer & solution

Answer: (A) Budgeting in which managers responsible for budgets help prepare them

It improves motivation but may create slack.

Question 20

What is an imposed (top-down) budget?

  1. A flexible budget
  2. A budget set by senior management with little input from lower managers
  3. A participative budget
  4. A rolling budget
Show answer & solution

Answer: (B) A budget set by senior management with little input from lower managers

It is quicker but may demotivate.

Question 21

What is the role of a budget committee?

  1. Coordinating, reviewing and approving the budgets of all departments
  2. Collecting taxes
  3. Paying wages
  4. Auditing the accounts
Show answer & solution

Answer: (A) Coordinating, reviewing and approving the budgets of all departments

It usually includes senior managers.

Question 22

What is a budget manual?

  1. A stock ledger
  2. A sales invoice
  3. A record of actual costs
  4. A document setting out budget procedures, timetables and responsibilities
Show answer & solution

Answer: (D) A document setting out budget procedures, timetables and responsibilities

It guides those preparing budgets.

Question 23

What is responsibility accounting?

  1. A system ignoring control
  2. A tax system
  3. A system holding managers accountable for costs and revenues they control
  4. An audit system
Show answer & solution

Answer: (C) A system holding managers accountable for costs and revenues they control

Reports follow the lines of authority.

Question 24

What is management by exception?

  1. Reviewing every item equally
  2. Focusing management attention on significant variances from budget
  3. Ignoring variances
  4. Approving all spending
Show answer & solution

Answer: (B) Focusing management attention on significant variances from budget

It saves management time.

Question 25

What is feedforward control?

  1. Comparing actual results with budget after the event
  2. Ignoring forecasts
  3. Comparing forecast results with targets so that action can be taken before problems occur
  4. Auditing past results
Show answer & solution

Answer: (C) Comparing forecast results with targets so that action can be taken before problems occur

It is forward-looking.

Question 26

What is feedback control?

  1. Preparing tax returns
  2. Ignoring variances
  3. Forecasting the future only
  4. Comparing actual results with the budget and taking corrective action
Show answer & solution

Answer: (D) Comparing actual results with the budget and taking corrective action

Variance reports are a form of feedback.

Question 27

What is "beyond budgeting"?

  1. An approach that replaces fixed annual budgets with adaptive targets and rolling forecasts
  2. A larger budget
  3. A cash budget
  4. A budget for next decade
Show answer & solution

Answer: (A) An approach that replaces fixed annual budgets with adaptive targets and rolling forecasts

It aims to make organisations more flexible.

Question 28

What is goal congruence in budgeting?

  1. When costs are zero
  2. When managers' personal goals align with the organisation's goals
  3. When sales equal costs
  4. When budgets are always met
Show answer & solution

Answer: (B) When managers' personal goals align with the organisation's goals

Good budget systems encourage it.

Question 29

What dysfunctional behaviour can a "use it or lose it" budget rule encourage?

  1. Saving money
  2. Unnecessary spending near year-end to protect next year's budget
  3. Accurate forecasting
  4. Lower costs
Show answer & solution

Answer: (B) Unnecessary spending near year-end to protect next year's budget

Managers fear budget cuts.

Question 30

What is the labour cost budget if production is 10,500 units, each needs 0.5 hours and the rate is Rs 400 per hour?

  1. Rs 4,200,000
  2. Rs 1,050,000
  3. Rs 2,000,000
  4. Rs 2,100,000
Show answer & solution

Answer: (D) Rs 2,100,000

5,250 hours × 400.

Question 31

What is the closing cash balance if opening cash is Rs 100,000, receipts Rs 540,000 and payments Rs 600,000?

  1. Rs 60,000
  2. Rs 160,000
  3. Rs 40,000
  4. Rs 140,000
Show answer & solution

Answer: (C) Rs 40,000

100,000 + 540,000 − 600,000.

Question 32

What does a negative closing balance in a cash budget indicate?

  1. The business needs financing, such as an overdraft, for that period
  2. A profit
  3. Excess cash
  4. A tax refund
Show answer & solution

Answer: (A) The business needs financing, such as an overdraft, for that period

Early warning allows finance to be arranged.

Question 33

Which components are identified in time series analysis for sales forecasting?

  1. Only fixed costs
  2. Only variable costs
  3. Tax and interest
  4. Trend, seasonal variations, cyclical variations and random variations
Show answer & solution

Answer: (D) Trend, seasonal variations, cyclical variations and random variations

Seasonal patterns are common in many industries.

Question 34

What is the purpose of a moving average in forecasting?

  1. Measuring liquidity
  2. Valuing assets
  3. Smoothing out short-term fluctuations to show the underlying trend
  4. Calculating tax
Show answer & solution

Answer: (C) Smoothing out short-term fluctuations to show the underlying trend

It averages values over several periods.

Question 35

What is a capital expenditure budget?

  1. A budget for raw materials
  2. A budget for planned spending on long-term assets
  3. A budget for wages
  4. A sales budget
Show answer & solution

Answer: (B) A budget for planned spending on long-term assets

It links to investment appraisal.

Question 36

What is a budget centre?

  1. A section of the organisation for which a budget is prepared and a manager is responsible
  2. A government office
  3. A bank
  4. A stock location
Show answer & solution

Answer: (A) A section of the organisation for which a budget is prepared and a manager is responsible

It is the unit of budgetary control.

Question 37

Which benefit is a main reason organisations prepare budgets?

  1. Avoiding audits
  2. Eliminating all risks
  3. Avoiding taxes
  4. Planning, coordination, communication, motivation and control
Show answer & solution

Answer: (D) Planning, coordination, communication, motivation and control

Budgets serve several purposes together.

Question 38

What is a favourable variance?

  1. A zero variance
  2. A variance that increases profit compared with budget
  3. A variance that reduces profit
  4. A tax variance
Show answer & solution

Answer: (B) A variance that increases profit compared with budget

Lower costs or higher revenue cause it.

Question 39

What is an adverse variance?

  1. A zero variance
  2. A variance that increases profit
  3. A variance that reduces profit compared with budget
  4. A cash surplus
Show answer & solution

Answer: (C) A variance that reduces profit compared with budget

Higher costs or lower revenue cause it.

Question 40

What is a master budget's budgeted statement of financial position used for?

  1. Recording actual transactions
  2. Valuing inventory under IAS 2
  3. Showing the expected assets, liabilities and equity at the end of the budget period
  4. Calculating payroll
Show answer & solution

Answer: (C) Showing the expected assets, liabilities and equity at the end of the budget period

It completes the master budget.