When may a professional accountant disclose confidential information?
Show answer & solution
Answer: (C) When permitted by the client, required by law, or required by a professional duty
Disclosure must be appropriate and limited.
Auditing · Professional Ethics & Independence
40 questions, each with the answer and a worked solution.
Practice interactively and track your score →When may a professional accountant disclose confidential information?
Answer: (C) When permitted by the client, required by law, or required by a professional duty
Disclosure must be appropriate and limited.
What should an auditor consider before disclosing confidential information?
Answer: (B) Whether all relevant information is known, the type of disclosure and the recipients
Professional judgement is needed.
What does NOCLAR stand for in the Code of Ethics?
Answer: (D) Non-compliance with laws and regulations
It covers how to respond to suspected illegal acts.
What is the main objective of the NOCLAR provisions?
Answer: (B) Acting in the public interest when the accountant becomes aware of possible illegal acts by a client
They may permit disclosure to authorities.
What is the first step when an auditor becomes aware of suspected non-compliance with laws by a client?
Answer: (A) Obtain an understanding of the matter and discuss it with an appropriate level of management
Escalation follows if needed.
What may an auditor do under NOCLAR if management does not respond appropriately to serious non-compliance?
Answer: (D) Consider further action, including disclosure to an appropriate authority or withdrawal
Legal advice may be needed.
What is "tipping off" in anti-money-laundering rules?
Answer: (C) Informing a suspect that a report has been or will be made to the authorities
Tipping off is an offence.
To which body are suspicious transaction reports made in Pakistan under anti-money-laundering law?
Answer: (D) Financial Monitoring Unit (FMU)
The Anti-Money Laundering Act 2010 applies.
What is professional clearance?
Answer: (B) Contacting the existing auditor before accepting appointment to ask for any professional reasons not to accept
It is required by ICAP's Code.
What should the proposed auditor do if the client refuses permission to contact the existing auditor?
Answer: (C) Decline the appointment
Refusal is a warning sign.
What is a conflict of interest for an audit firm?
Answer: (A) A situation where the firm's interests or those of two clients conflict, threatening objectivity
Examples include advising two bidders for the same company.
Which safeguard is used when a firm acts for two competing clients?
Answer: (B) Separate engagement teams and information barriers (confidentiality walls)
Clients should be informed and consent where needed.
What is a "second opinion" request?
Answer: (C) A request from a non-client entity for the firm's view on applying accounting standards to a specific situation
The firm should contact the existing auditor if appropriate.
What is the subject of International Standard on Quality Management 1 (ISQM 1)?
Answer: (A) A firm's system of quality management for audits, reviews and other engagements
It replaced ISQC 1.
How many components does a system of quality management have under ISQM 1?
Answer: (D) Eight
They include governance, risk assessment and monitoring.
Which is a component of the system of quality management under ISQM 1?
Answer: (A) Governance and leadership
Others include resources and information and communication.
What is the risk assessment process in ISQM 1?
Answer: (C) Establishing quality objectives, identifying and assessing quality risks and designing responses
It is a key change from ISQC 1.
Which standard deals with engagement quality reviews?
Answer: (B) ISQM 2
It covers appointment and eligibility of reviewers.
What cooling-off period does ISQM 2 require before an engagement partner can become the engagement quality reviewer on the same engagement?
Answer: (D) Two years
This protects the reviewer's objectivity.
Which standard deals with quality management for an audit engagement?
Answer: (B) ISA 220 (Revised)
The engagement partner takes overall responsibility.
Who is responsible for managing and achieving quality on an audit engagement under ISA 220?
Answer: (C) The engagement partner
The partner must be sufficiently involved.
What is "monitoring and remediation" in ISQM 1?
Answer: (A) Evaluating whether the quality system is working and correcting deficiencies
It includes inspection of completed engagements.
How often must a firm evaluate its system of quality management under ISQM 1?
Answer: (D) At least annually
The leadership evaluates and concludes on the system.
What is "client acceptance and continuance" in quality management?
Answer: (A) Deciding whether to accept or continue a client based on integrity, competence and ethics
It reduces the risk of association with dishonest clients.
Why should an auditor consider the integrity of a prospective client's management?
Answer: (D) Dishonest management increases the risk of fraud and of being associated with misleading information
Background checks help assess integrity.
What is the purpose of consultation on difficult or contentious matters?
Answer: (C) Obtaining appropriate expert advice and documenting conclusions
ISA 220 requires consultation where needed.
What should happen to differences of opinion within the engagement team?
Answer: (B) They should be resolved under the firm's policies before the report is issued
Resolution must be documented.
What is the purpose of ICAP's Quality Control Review (QCR) programme in Pakistan?
Answer: (C) Reviewing whether audit firms comply with quality control standards and professional requirements
Firms are given ratings after review.
What is the role of the Audit Oversight Board in quality management in Pakistan?
Answer: (B) Inspecting audit firms that audit public interest companies and taking action for deficiencies
It operates under the SECP framework.
Why is confidentiality important even after the client relationship ends?
Answer: (A) The duty of confidentiality continues after the engagement ends
Information must still be protected.
What is a "confidentiality wall" (information barrier)?
Answer: (D) Procedures that prevent confidential information from passing between teams serving different clients
It is used to manage conflicts of interest.
What should an existing auditor do when asked by a proposed successor for information?
Answer: (B) Respond, with the client's permission, giving any professional reasons against accepting
Confidentiality applies, so permission is needed.
What is the auditor's duty on discovering that a client has committed a tax fraud?
Answer: (B) Consider legal obligations, discuss with management, and assess implications for the audit and relationship
Professional advice may be needed.
What is the main purpose of an audit firm's ethics partner?
Answer: (D) Providing guidance and oversight on ethical and independence matters within the firm
Firms appoint leadership for ethics.
What information must ISQM 1 require firms to communicate externally in some cases?
Answer: (C) Information about the firm's system of quality management, such as transparency reports
Transparency supports public trust.
What is the role of "resources" in ISQM 1?
Answer: (A) Ensuring the firm has appropriate human, technological and intellectual resources
Resources include competent people and audit tools.
What is "engagement performance" in ISQM 1?
Answer: (B) Policies ensuring engagements are directed, supervised and reviewed appropriately
It covers consultation and differences of opinion.
What is "information and communication" in ISQM 1?
Answer: (C) Obtaining, generating and sharing information needed for the quality system
It includes communication with network firms.
What should an auditor do when a deficiency is found in the firm's quality system?
Answer: (A) Evaluate its severity, investigate root causes and remediate
Root cause analysis is required.
What is the main purpose of engagement quality review under ISQM 2?
Answer: (D) Objectively evaluating significant judgements and conclusions of the engagement team before the report is issued
It is required for listed entities and other designated engagements.